5745 N LEMP AVE 91601
Certificate Information: 5745 N LEMP AVE 91601
- Application / Permit
- 25014-20000-04350
- Plan Check / Job No.
- B25VN28409
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- BEDROOM ADDITION AT REAR & CONVERT (E) BEDROOM INTO BATHROOM & HALLWAY.
- Permit Issued
- Issued on 12/29/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/28/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2025 | HAYATO TSUCHIYA |
| Corrections Issued | 10/2/2025 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 10/3/2025 | APPLICANT |
| Plan Check Approved | 10/17/2025 | ANGELICA DAVE |
| No Progress | 12/16/2025 | JEROME MAGAT PALMA |
| Plan Check Approved | 12/16/2025 | JEROME MAGAT PALMA |
| Issued | 12/29/2025 | APPLICANT |
| CofO in Progress | 5/28/2026 | RAUL OLAGI |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/6/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2025 | DAVID LOPEZ |
Contact Information
| Contractor | Nittay Inc; Lic. No.: 1033506-B | 17941 VENTURA BLVD #204 ENCINO, CA 91316 |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/9/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 1/12/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 1/12/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2026 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/2/2026 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/2/2026 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2026 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 2/2/2026 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/6/2026 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/6/2026 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2026 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 2/6/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 2/6/2026 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/6/2026 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 2/6/2026 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/24/2026 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/24/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 2/24/2026 | Approved | JAVIER RAMOS JR |
| Insulation | 2/24/2026 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/24/2026 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/3/2026 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 3/3/2026 | Approved | JAVIER RAMOS JR |
| Final | 5/28/2026 | OK to Issue CofO | RAUL OLAGI |
| Green Building Final | 5/28/2026 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 5/28/2026 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 5/28/2026 | Approved | RAUL OLAGI |