5254-5258 N IRVINE AVE 91601
Certificate Information: 5254-5258 N IRVINE AVE 91601
- Application / Permit
- 25014-20000-04269
- Plan Check / Job No.
- B25VN27861
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED JUNIOR ACCESSORY DWELLING UNIT ADDITION TO EX 1-STORY SINGLE FAMILY DWELLING PER GCS 66323(a)(1) & 66333. ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/19/2025
- Issuing Office
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2025 | HAYATO TSUCHIYA |
| Corrections Issued | 9/27/2025 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 9/29/2025 | APPLICANT |
| Plan Check Approved | 12/19/2025 | GIOVANNY CHAVEZ |
| Issued | 12/19/2025 | APPLICANT |
| CofO in Progress | 4/3/2026 | JAVIER RAMOS JR |
| CofO Issued | 4/30/2026 | RUBEN SALAS |
| Permit Finaled | 4/30/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/30/2025 | ROSE STEIN-WENDT |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2025 | ROSE STEIN-WENDT |
| Roof/Waste drainage to street | Cleared | 9/30/2025 | ROSE STEIN-WENDT |
| Sewer availability | Cleared | 9/30/2025 | ROSE STEIN-WENDT |
| Miscellaneous | Cleared | 11/7/2025 | SASHA KASSAB |
| Specific Plan | Cleared | 11/7/2025 | SASHA KASSAB |
| Specific Plan | Cleared | 11/7/2025 | SASHA KASSAB |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/23/2025 | Partial Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 1/8/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 1/8/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Sewer | 1/8/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 1/8/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Deputy Drilled-In Anchors | 1/9/2026 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 1/9/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 1/15/2026 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 1/15/2026 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2026 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 1/15/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 1/15/2026 | Approved | JAVIER RAMOS JR |
| MERV13>=Rough | 1/15/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/15/2026 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 1/15/2026 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 1/20/2026 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 1/20/2026 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 1/20/2026 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 1/22/2026 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/6/2026 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 3/6/2026 | Approved | JAVIER RAMOS JR |
| Final | 3/6/2026 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 3/6/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 3/6/2026 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 3/6/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 3/6/2026 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 3/6/2026 | SGSOV Not Ready | JAVIER RAMOS JR |
| Smoke Detectors | 3/6/2026 | Approved | JAVIER RAMOS JR |
| Final | 4/3/2026 | OK to Issue CofO | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/3/2026 | SGSOV Approved | JAVIER RAMOS JR |