11110-11112 W WICKS ST 91352
Certificate Information: 11110-11112 W WICKS ST 91352
- Application / Permit
- 25014-20000-04257
- Plan Check / Job No.
- B25VN27718
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD TO THE EXISTING ATTACHED GARAGE AND CONVERT TO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (e).
- Permit Issued
- Issued on 4/17/2026
- Issuing Office
- Current Status
- Issued on 4/17/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2025 | MINA HABILI |
| Corrections Issued | 9/27/2025 | MINA HABILI |
| Applicant returned to address corrections | 3/19/2026 | MINA HABILI |
| Applicant returned to address corrections | 3/26/2026 | MINA HABILI |
| Applicant returned to address corrections | 4/9/2026 | SERGIO MUNIZ |
| Plan Check Approved | 4/16/2026 | SERGIO MUNIZ |
| Issued | 4/17/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/22/2025 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 12/5/2025 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2026 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 3/19/2026 | MINA HABILI |
| Specific Plan | Cleared | 3/24/2026 | DANG NGUYEN |
| Private sewage disp. approval | Cleared | 4/7/2026 | MICHAEL TEMPLE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/26/2026 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 7/1/2026 | Partial Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 7/10/2026 | Corrections Issued | MATTHEW NELSON |
| METHANE-Barrier | 7/10/2026 | Approved | MATTHEW NELSON |
| METHANE-Subgrade | 7/10/2026 | Approved | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 7/15/2026 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 7/17/2026 | Approved | DAVID MATSON |