4512-4514 N CEDROS AVE 91403

Certificate Information: 4512-4514 N CEDROS AVE 91403

Application / Permit
25014-20000-04239
Plan Check / Job No.
B25VN27629
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
MAJOR REMODEL AND 2-STORY ADDITION TO (E) SFD TO BECOME AN IRR SHAPED 38' x 74'-3" TWO-STORY SINGLE FAMILY DWELLING W/ ATT 2-CAR GARAGE & ATT 2-STORY ACCESSORY DWELLING UNIT PER CITY ORDINANCE (LAMC 12.22 A.33(c) AND (e)).; NFPA-13D THRU-OUT
Permit Issued
Issued on 11/10/2025
Issuing Office
Current Status
Issued on 11/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/19/2025 APPLICANT
Assigned to Plan Check Engineer 9/25/2025 SEAN SHAHMIRI
Assigned to Zoning Architect 9/25/2025 NICOLE SALEEBA
Corrections Issued 10/1/2025 SEAN SHAHMIRI
Quality Review Completed 10/2/2025 STEVEN KIM
Building Plans Picked Up 10/3/2025 APPLICANT
Applicant returned to address corrections 11/5/2025 SEAN SHAHMIRI
Plan Check Approved 11/5/2025 SEAN SHAHMIRI
Issued 11/10/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/7/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/14/2025 BIAINA HARITUNIAN
Sewer availability Cleared 10/14/2025 BIAINA HARITUNIAN
Supp. Use District POD/CDO/TDO Cleared 10/14/2025 BRENNEN OBETO
Roof/Waste drainage to street Cleared 10/27/2025 BIAINA HARITUNIAN
Zoning Plan Check Cleared 10/29/2025 NICOLE SALEEBA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/23/2025 Approved MISAEL ESPARZA
Footing/Foundation/Slab 1/12/2026 Partial Approval MISAEL ESPARZA
Grading Pre-Inspection 1/12/2026 Partial Inspection MISAEL ESPARZA
PLUMBING-Rough 1/12/2026 Approved MISAEL ESPARZA
Footing/Foundation/Slab 1/15/2026 Approved MISAEL ESPARZA
Deputy Steel/Welding 1/22/2026 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/27/2026 Partial Approval MISAEL ESPARZA
Deputy Wood Construction 2/2/2026 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/2/2026 Partial Approval MISAEL ESPARZA
Insulation 2/12/2026 Not Ready for Inspection MISAEL ESPARZA
Insulation 2/25/2026 Corrections Issued MISAEL ESPARZA
Insulation 3/2/2026 Partial Approval MISAEL ESPARZA
Drywall Nailing 3/5/2026 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/5/2026 Partial Approval MISAEL ESPARZA
Green Building Rough 3/5/2026 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 3/18/2026 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 3/18/2026 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 3/20/2026 Approved MISAEL ESPARZA
HVAC-Rough 3/23/2026 Approved MISAEL ESPARZA
ELECTRICAL-Rough 4/1/2026 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 4/13/2026 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 4/20/2026 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 4/20/2026 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 4/24/2026 Approved MICHAEL CORTEZ
Deputy Wood Construction 4/24/2026 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/24/2026 Approved MICHAEL CORTEZ
Green Building Rough 4/24/2026 Approved MICHAEL CORTEZ
Special/Order Compliance 4/24/2026 Corrections Issued MICHAEL CORTEZ
Insulation 4/27/2026 Approved MISAEL ESPARZA
Drywall Nailing 4/30/2026 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 4/30/2026 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 5/6/2026 Approved MICHAEL CORTEZ
Drywall Nailing 5/8/2026 Approved MISAEL ESPARZA
Gas Test 5/8/2026 Not Ready for Inspection MISAEL ESPARZA