10317 N GLORY AVE 91042
Certificate Information: 10317 N GLORY AVE 91042
- Application / Permit
- 25014-20000-04220
- Plan Check / Job No.
- B25VN27438
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO SFD
- Permit Issued
- Issued on 11/5/2025
- Issuing Office
- Valley
- Current Status
- Issued on 11/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2025 | JESSE ARELLANO |
| Corrections Issued | 9/24/2025 | JESSE ARELLANO |
| Building Plans Picked Up | 9/26/2025 | APPLICANT |
| Applicant returned to address corrections | 10/17/2025 | ANGELICA DAVE |
| Plan Check Approved | 11/5/2025 | MOHAMMAD ESMAILI |
| Issued | 11/5/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/3/2025 | MANUEL TEJADA |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 10/10/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Gt Remodeling Inc; Lic. No.: 1091310-B | 15250 VENTURA BLVD SHERMAN OAKS, CA 91403 |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/4/2025 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 12/9/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Excavation/Setback/Form/Re-Bar | 12/15/2025 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 1/12/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 1/12/2026 | Partial Approval | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2026 | Partial Approval | DAVID MATSON |
| Insulation | 1/27/2026 | Partial Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 3/10/2026 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 3/10/2026 | Approved | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2026 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 3/10/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 3/10/2026 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 3/23/2026 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 3/23/2026 | Approved | NICHOLAS TROWBRIDGE |
| Shower Pan | 3/23/2026 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 4/7/2026 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 5/29/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 5/29/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 5/29/2026 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 5/29/2026 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 5/29/2026 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 5/29/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 6/1/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |