13066 W GARBER ST 91331

Certificate Information: 13066 W GARBER ST 91331

Application / Permit
25014-20000-04204
Plan Check / Job No.
B25VN27278
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan ADDITION TO (E) SFD FOR A NEW BEDROOM. ALL WORK PER WFPP. (E) 2-CAR GARAGE TO BE CONVERTED INTO ADU 2 of 2
Permit Issued
Issued on 11/19/2025
Issuing Office
Current Status
CofO Issued on 4/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2025 APPLICANT
Assigned to Plan Check Engineer 9/24/2025 SAMUEL GONZALEZ
Corrections Issued 9/25/2025 SAMUEL GONZALEZ
Plan Check Approved 11/11/2025 SAMUEL GONZALEZ
Issued 11/19/2025 APPLICANT
CofO in Progress 3/3/2026 MICHEL ABAJAN
Permit Finaled 4/10/2026 RUBEN SALAS
CofO Issued 4/10/2026 RUBEN SALAS
Permit Finaled 4/10/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/14/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/15/2025 BIAINA HARITUNIAN

Contact Information

Contractor Ultimate Green Construction Inc; Lic. No.: 1023605-B       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/3/2025 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 12/4/2025 Approved MICHEL ABAJAN
Footing/Foundation/Slab 12/4/2025 Approved MICHEL ABAJAN
METHANE-Barrier 12/4/2025 Approved MICHEL ABAJAN
METHANE-Subgrade 12/4/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 12/4/2025 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 12/22/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 12/22/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/22/2025 Partial Approval MICHEL ABAJAN
Green Building Rough 12/22/2025 Approved MICHEL ABAJAN
HVAC-Rough 12/22/2025 Approved MICHEL ABAJAN
METHANE-Rough 12/22/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 12/22/2025 Approved MICHEL ABAJAN
Underground Mechanical 12/22/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/23/2025 Partial Approval MICHEL ABAJAN
Insulation 1/8/2026 Approved MICHEL ABAJAN
Drywall Nailing 1/12/2026 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/12/2026 Approved MICHEL ABAJAN
Shower Pan 1/12/2026 Approved MICHEL ABAJAN
ELECTRICAL-Final 3/2/2026 Approved MICHEL ABAJAN
Final 3/2/2026 OK to Issue CofO MICHEL ABAJAN
Green Building Final 3/2/2026 Approved MICHEL ABAJAN
HVAC-Final 3/2/2026 Approved MICHEL ABAJAN
PLUMBING-Final 3/2/2026 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/2/2026 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 3/2/2026 Approved MICHEL ABAJAN