6423 N SHELTONDALE AVE 91307
Certificate Information: 6423 N SHELTONDALE AVE 91307
- Application / Permit
- 25014-20000-04201
- Plan Check / Job No.
- B25VN27214
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN- NEW ADDITION TO EXISTING SINGLE FAMILY DWELLING UNIT AND REPLACING EXISTING ALUMINUM PATIO COVER WITH WOOD FRAMING PATIO COVER. ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/19/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/19/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2025 | PINANK PATEL |
| Corrections Issued | 9/20/2025 | PINANK PATEL |
| Plan Check Approved | 10/28/2025 | ARAMIK SHAHMIRZAIAN |
| Issued | 11/19/2025 | APPLICANT |
| CofO in Progress | 5/19/2026 | TROY SANDERS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/23/2025 | GEVORK KARAPETYAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 10/24/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Ete Real Estate Developer; Lic. No.: 814705-B | , |
| Engineer | Bui,, Mai Phuong; Lic. No.: C61280 | 7445 LURLINE AVE WINNETKA, CA 91306 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/11/2025 | Approved | TROY SANDERS |
| Deputy Drilled-In Anchors | 12/18/2025 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 12/19/2025 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2026 | Partial Approval | TROY SANDERS |
| Green Building Rough | 1/7/2026 | Not Ready for Inspection | TROY SANDERS |
| BUILDING-Rough-Frame | 2/19/2026 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 2/19/2026 | Approved | TROY SANDERS |
| Green Building Rough | 2/19/2026 | Approved | TROY SANDERS |
| HVAC-Rough | 2/19/2026 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 2/19/2026 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 2/19/2026 | Approved | TROY SANDERS |
| Wood Frame | 2/19/2026 | Approved | TROY SANDERS |
| Insulation | 2/23/2026 | Approved | ARUTYUN MADATYAN |
| Shower Pan | 2/23/2026 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 3/2/2026 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 3/2/2026 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Final | 5/18/2026 | Approved | TROY SANDERS |
| Final | 5/18/2026 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 5/18/2026 | Approved | TROY SANDERS |
| PLUMBING-Final | 5/18/2026 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/18/2026 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 5/18/2026 | Approved | TROY SANDERS |