10849 N SWINTON AVE 91344

Certificate Information: 10849 N SWINTON AVE 91344

Application / Permit
25014-20000-04181
Plan Check / Job No.
B25VN27103
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE with addition INTO detached ADU per LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 1/13/2026
Issuing Office
Current Status
CofO Issued on 6/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2025 APPLICANT
Assigned to Plan Check Engineer 9/24/2025 CARLOS MONTES
Corrections Issued 9/25/2025 CARLOS MONTES
Applicant returned to address corrections 12/2/2025 CARLOS MONTES
Plan Check Approved 12/10/2025 CARLOS MONTES
Issued 1/13/2026 APPLICANT
CofO in Progress 5/29/2026 CHRISTOPHER ROJAS
Permit Finaled 6/8/2026 RUBEN SALAS
CofO Issued 6/8/2026 RUBEN SALAS
Permit Finaled 6/8/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/22/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 10/22/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 10/24/2025 SAFA JAVANMARDI
Sewer availability Cleared 10/24/2025 SAFA JAVANMARDI
Construction near power lines Cleared 11/25/2025 GEVORK KARAPETYAN

Contact Information

Contractor Glenwood Building Company Llc; Lic. No.: 1052602-B       ,
Engineer Ursu,, Dragos; Lic. No.: NA79963       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/26/2026 Not Ready for Inspection KIRK SANDERS
Underground Mechanical 1/26/2026 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 1/30/2026 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/6/2026 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 3/6/2026 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/6/2026 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 3/6/2026 Approved JAVIER RAMOS JR
PLUMBING-Rough 3/6/2026 Approved JAVIER RAMOS JR
Sewer 3/6/2026 Approved JAVIER RAMOS JR
Underground Mechanical 3/6/2026 Partial Approval JAVIER RAMOS JR
Insulation 3/19/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 3/19/2026 Partial Approval CHRISTOPHER ROJAS
Shower Pan 3/19/2026 Approved CHRISTOPHER ROJAS
Drywall Nailing 3/23/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 3/26/2026 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/21/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 5/21/2026 Corrections Issued CHRISTOPHER ROJAS
Final 5/21/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 5/21/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 5/21/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 5/21/2026 Corrections Issued CHRISTOPHER ROJAS
MERV13>=Final 5/21/2026 Approved CHRISTOPHER ROJAS
MERV13>=Rough 5/21/2026 Approved CHRISTOPHER ROJAS
PLUMBING-Final 5/21/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 5/21/2026 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 5/21/2026 Approved CHRISTOPHER ROJAS
Final 5/27/2026 OK to Issue CofO CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 5/27/2026 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 5/27/2026 Approved CHRISTOPHER ROJAS