14402 W MERCER ST 91331
Certificate Information: 14402 W MERCER ST 91331
- Application / Permit
- 25014-20000-04172
- Plan Check / Job No.
- B25VN27005
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: ADDITION TO (E) DETACHED ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 11/26/2025
- Issuing Office
- Current Status
- CofO Issued on 5/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2025 | GEORGE ALVAREZ |
| Corrections Issued | 9/22/2025 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 10/30/2025 | ZAW HAN |
| Plan Check Approved | 11/25/2025 | FERNANDO FLORES |
| Issued | 11/26/2025 | APPLICANT |
| CofO in Progress | 3/26/2026 | JENNIFER RABUCHIN |
| Permit Finaled | 5/19/2026 | RUBEN SALAS |
| CofO Issued | 5/19/2026 | RUBEN SALAS |
| Permit Finaled | 5/19/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 9/25/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 9/25/2025 | MICHAEL BROWN |
| Construction near power lines | Cleared | 11/21/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/10/2025 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/15/2025 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 12/15/2025 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 12/15/2025 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/30/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/30/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 12/30/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/30/2025 | Partial Approval | JENNIFER RABUCHIN |
| MERV13>=Rough | 12/30/2025 | Approved | JENNIFER RABUCHIN |
| METHANE-Rough | 12/30/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/30/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 12/31/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 1/5/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/5/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 1/5/2026 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/7/2026 | Approved | JENNIFER RABUCHIN |
| Final | 3/12/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 3/12/2026 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/12/2026 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 3/12/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 3/25/2026 | Approved | JENNIFER RABUCHIN |
| Final | 3/25/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 3/25/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 3/25/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 3/25/2026 | Approved | JENNIFER RABUCHIN |