10034 N GLORIA AVE 91343

Certificate Information: 10034 N GLORIA AVE 91343

Application / Permit
25014-20000-04149
Plan Check / Job No.
B25VN26840
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(2)
Permit Issued
Issued on 11/26/2025
Issuing Office
Current Status
Issued on 11/26/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/15/2025 APPLICANT
Assigned to Plan Check Engineer 9/17/2025 DANIEL YIP
Corrections Issued 9/18/2025 DANIEL YIP
Applicant returned to address corrections 10/1/2025 DANIEL YIP
Applicant returned to address corrections 10/23/2025 DANIEL YIP
Plan Check Approved 10/28/2025 DANIEL YIP
Issued 11/26/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/19/2025 ALEXANDER HELFER
Address approval Cleared 9/27/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/27/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/27/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/29/2025 LEE GUILBEAUX
Sewer availability Cleared 9/29/2025 LEE GUILBEAUX
Construction within easement Cleared 10/25/2025 ENRIQUE ACOSTA

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: NA53080       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/9/2026 Partial Inspection CHRISTOPHER ROJAS
Underground Mechanical 3/9/2026 Partial Approval CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 3/16/2026 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 3/17/2026 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/1/2026 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/2/2026 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/2/2026 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/8/2026 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/8/2026 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 5/8/2026 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 5/8/2026 Corrections Issued CHRISTOPHER ROJAS
HVAC-Rough 5/8/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 5/8/2026 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/18/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 5/18/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Insulation 5/18/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 5/18/2026 Corrections Issued CHRISTOPHER ROJAS
Shower Pan 5/18/2026 Approved CHRISTOPHER ROJAS
Drywall Nailing 5/26/2026 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 5/26/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 5/26/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 5/26/2026 Approved CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 5/26/2026 Approved CHRISTOPHER ROJAS
Sewer 5/26/2026 Approved CHRISTOPHER ROJAS