10330-10332 N DEMPSEY AVE 91344

Certificate Information: 10330-10332 N DEMPSEY AVE 91344

Application / Permit
25014-20000-04080
Plan Check / Job No.
B25VN26459
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: COVNERSION OF (E) ATTACHED GARAGE WITH ADDITIONS TO CREATE A 2-STORY ATTACHED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c) and (e) PER ENGINEERING
Permit Issued
Issued on 3/5/2026
Issuing Office
Current Status
Issued on 3/5/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/11/2025 APPLICANT
Assigned to Plan Check Engineer 9/18/2025 ALFRED RAMIREZ
Assigned to Zoning Architect 9/18/2025 ERIC ROMERO
Corrections Issued 9/24/2025 ALFRED RAMIREZ
Quality Review Completed 9/26/2025 STEVEN KIM
Applicant returned to address corrections 1/13/2026 ALFRED RAMIREZ
Applicant returned to address corrections 2/12/2026 ALFRED RAMIREZ
Applicant returned to address corrections 2/20/2026 ALFRED RAMIREZ
Plan Check Approved 3/4/2026 ALFRED RAMIREZ
Issued 3/5/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/6/2025 STEVE MELGAR
Roof/Waste drainage to street Cleared 11/6/2025 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 11/7/2025 STEVE MELGAR
Sewer availability Cleared 11/7/2025 STEVE MELGAR
Zoning Plan Check Cleared 2/16/2026 ERIC ROMERO

Contact Information

Contractor Dhs Ventures Inc; Lic. No.: 1047699-B       ,
Contractor La Ccs; Lic. No.: 1047699-B       ,
Engineer Broderick,, James Mark; Lic. No.: C91994 118 LYNNWOOD DR      CLEARFIELD, UT 84015

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/16/2026 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 3/20/2026 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 3/27/2026 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/22/2026 Partial Approval CHRISTOPHER ROJAS
Special/Order Compliance 4/22/2026 Corrections Issued CHRISTOPHER ROJAS
Deputy Wood Construction 4/30/2026 Conditional Approval JOSE AVILA
BUILDING-Rough-Frame 5/8/2026 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/8/2026 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 5/8/2026 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 5/8/2026 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/18/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 5/18/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/1/2026 Partial Approval CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 6/10/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Wood Frame 6/10/2026 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/26/2026 Approved CHRISTOPHER ROJAS
Insulation 6/26/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/26/2026 Partial Approval CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 6/26/2026 Approved CHRISTOPHER ROJAS
Drywall Nailing 7/2/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 7/8/2026 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 7/9/2026 Partial Approval CHRISTOPHER ROJAS
Sewer 7/9/2026 Approved CHRISTOPHER ROJAS
Shower Pan 7/9/2026 Approved CHRISTOPHER ROJAS