4500 S GRAMERCY PL 90062
Certificate Information: 4500 S GRAMERCY PL 90062
- Application / Permit
- 25014-20000-04068
- Plan Check / Job No.
- B25VN26345
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(A)(2)
- Permit Issued
- Issued on 10/9/2025
- Issuing Office
- Current Status
- CofO Issued on 3/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 9/16/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 9/17/2025 | APPLICANT |
| Plan Check Approved | 10/9/2025 | MINA HABILI |
| Issued | 10/9/2025 | APPLICANT |
| CofO in Progress | 3/2/2026 | SABAS ALONSO |
| Permit Finaled | 3/2/2026 | DEROLD HAUFF |
| CofO Issued | 3/2/2026 | DEROLD HAUFF |
| Permit Finaled | 3/2/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/18/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 9/19/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 9/30/2025 | TREVOR QUAN |
| Construction near power lines | Cleared | 10/2/2025 | TINA MIRANDA |
Contact Information
| Contractor | Soul Builders Inc; Lic. No.: 1103425-B | 8517 VALLEY FLORES DR WEST HILLS, CA 91304 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21731 VENTURA BLVD SUITE 110 WOODLAND HILLS, CA 91364 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/15/2025 | Partial Inspection | SABAS ALONSO |
| Underground Mechanical | 10/24/2025 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 10/30/2025 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 10/30/2025 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 11/6/2025 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 11/12/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2025 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 12/19/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 12/19/2025 | Corrections Issued | SABAS ALONSO |
| Deputy Wood Construction | 12/23/2025 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 12/23/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 12/23/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 12/23/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/30/2025 | Approved | ALEX COLIN |
| Green Building Rough | 12/30/2025 | Approved | ALEX COLIN |
| Insulation | 12/30/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 12/30/2025 | Partial Approval | ALEX COLIN |
| Shower Pan | 12/30/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 1/5/2026 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 1/7/2026 | Approved | SABAS ALONSO |
| Gas Test | 2/5/2026 | Approved | SABAS ALONSO |
| Sewer | 2/5/2026 | Approved | SABAS ALONSO |
| Underground Mechanical | 2/5/2026 | Approved | SABAS ALONSO |
| Final | 2/11/2026 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 2/11/2026 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 2/11/2026 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 2/11/2026 | Approved | SABAS ALONSO |
| Final | 2/19/2026 | Corrections Issued | SABAS ALONSO |
| Final | 2/24/2026 | Corrections Issued | SABAS ALONSO |
| Pre-Inspection | 2/25/2026 | Partial Inspection | SABAS ALONSO |
| Deputy Drilled-In Anchors | 2/27/2026 | Approved | SABAS ALONSO |
| Final | 2/27/2026 | OK to Issue CofO | SABAS ALONSO |