8410-8412 N NOBLE AVE 91343

Certificate Information: 8410-8412 N NOBLE AVE 91343

Application / Permit
25014-20000-04067
Plan Check / Job No.
B25VN26339
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMODEL TO (E) SFD AND CONVERT (E) ATTACHED GARAGE INTO A JUNIOR ACCESSORY DWELLING TO COMPLY WITH GCS 66323(a)(1) AND 66333 AND 2ND FLOOR ADDITION TO BE A 2ND FLOOR ATTACHED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c) and (e) PER ENGINEERING
Permit Issued
Issued on 10/29/2025
Issuing Office
Valley
Current Status
Issued on 10/29/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/9/2025 APPLICANT
Assigned to Plan Check Engineer 9/11/2025 ALFRED RAMIREZ
Assigned to Zoning Architect 9/11/2025 FRANCIS AHN
Corrections Issued 9/13/2025 ALFRED RAMIREZ
Quality Review Completed 9/17/2025 STEVEN KIM
Building Plans Picked Up 9/18/2025 APPLICANT
Applicant returned to address corrections 10/21/2025 ALFRED RAMIREZ
Plan Check Approved 10/29/2025 ALFRED RAMIREZ
Issued 10/29/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/19/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 9/19/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/22/2025 BIAINA HARITUNIAN
Sewer availability Cleared 9/22/2025 BIAINA HARITUNIAN
Miscellaneous Cleared 10/1/2025 ANNA VIDAL
Zoning Plan Check Cleared 10/28/2025 ALFRED RAMIREZ

Contact Information

Contractor No Limit Construction Corp; Lic. No.: 1082982-B 17001 BURTON ST      VAN NUYS, CA 91406
Engineer Mroczka,, Peter J; Lic. No.: C42648 9301 DARBY AVE APT 1      NORTHRIDGE, CA 91325

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Final 7/27/2026   

Inspection Request History

Pre-Inspection 2/4/2026 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 2/13/2026 Approved VINCENT HANLEY
Footing/Foundation/Slab 2/13/2026 Approved VINCENT HANLEY
PLUMBING-Rough 2/13/2026 Partial Approval VINCENT HANLEY
Sewer 2/13/2026 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 2/27/2026 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 3/6/2026 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/19/2026 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/10/2026 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 4/10/2026 Approved OGANES TARAKHCHYAN
Green Building Rough 4/10/2026 Approved OGANES TARAKHCHYAN
HVAC-Rough 4/10/2026 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/10/2026 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 4/10/2026 Approved OGANES TARAKHCHYAN
Shower Pan 4/10/2026 Approved OGANES TARAKHCHYAN
Insulation 4/16/2026 Approved GAREN HAYRAPETYAN
Drywall Nailing 4/21/2026 Approved GAREN HAYRAPETYAN
Final 6/29/2026 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 6/29/2026 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/29/2026 SGSOV Not Required JENNIFER RABUCHIN
Smoke Detectors 6/29/2026 Not Ready for Inspection JENNIFER RABUCHIN
Final 7/21/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 7/21/2026 Approved OGANES TARAKHCHYAN
Smoke Detectors 7/21/2026 Approved OGANES TARAKHCHYAN