11258 W CALIFA ST 91601

Certificate Information: 11258 W CALIFA ST 91601

Application / Permit
25014-20000-04054
Plan Check / Job No.
B25VN23218
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: REMODEL AND ADDITION TO (E) 1-STORY SFD PER ENGINEERING
Permit Issued
Issued on 12/20/2025
Issuing Office
Current Status
Issued on 12/20/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/25/2025 APPLICANT
Assigned to Plan Check Engineer 9/4/2025 ALFRED RAMIREZ
Corrections Issued 9/8/2025 ALFRED RAMIREZ
Quality Review Completed 9/12/2025 STEVEN KIM
Applicant returned to address corrections 9/29/2025 ALFRED RAMIREZ
Applicant returned to address corrections 11/4/2025 ALFRED RAMIREZ
Applicant returned to address corrections 11/12/2025 ALFRED RAMIREZ
Plan Check Approved 12/16/2025 ALFRED RAMIREZ
Issued 12/20/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/2/2025 DAVID LOPEZ
Sewer availability Cleared 12/2/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 12/3/2025 DAVID LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Scaduto,, Michael Anthony; Lic. No.: C77263 629 N MARGUERITA AVE      ALHAMBRA, CA 91801

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/12/2026 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 1/26/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 1/26/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 2/6/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 2/6/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 2/20/2026 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 2/20/2026 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/10/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/10/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/3/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Deputy Wood Construction 4/16/2026 Conditional Approval RAUL OLAGI