11258 W CALIFA ST 91601
Certificate Information: 11258 W CALIFA ST 91601
- Application / Permit
- 25014-20000-04054
- Plan Check / Job No.
- B25VN23218
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: REMODEL AND ADDITION TO (E) 1-STORY SFD PER ENGINEERING
- Permit Issued
- Issued on 12/20/2025
- Issuing Office
- Current Status
- Issued on 12/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2025 | ALFRED RAMIREZ |
| Corrections Issued | 9/8/2025 | ALFRED RAMIREZ |
| Quality Review Completed | 9/12/2025 | STEVEN KIM |
| Applicant returned to address corrections | 9/29/2025 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 11/4/2025 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 11/12/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 12/16/2025 | ALFRED RAMIREZ |
| Issued | 12/20/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/2/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 12/2/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2025 | DAVID LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Scaduto,, Michael Anthony; Lic. No.: C77263 | 629 N MARGUERITA AVE ALHAMBRA, CA 91801 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/12/2026 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 1/26/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 1/26/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 2/6/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 2/6/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 2/20/2026 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 2/20/2026 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 3/10/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Deputy Wood Construction | 4/16/2026 | Conditional Approval | RAUL OLAGI |