10363 N PATRICK AVE 91331

Certificate Information: 10363 N PATRICK AVE 91331

Application / Permit
25014-20000-03997
Plan Check / Job No.
B25VN25790
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELING UNIT PER GCS 66323(a)(2) W/ ADDITION. ALL WORK PER WFPP.
Permit Issued
Issued on 10/31/2025
Issuing Office
Current Status
Issued on 10/31/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/4/2025 APPLICANT
Assigned to Plan Check Engineer 9/10/2025 HAYATO TSUCHIYA
Corrections Issued 9/10/2025 HAYATO TSUCHIYA
Building Plans Picked Up 9/16/2025 APPLICANT
Plan Check Approved 10/31/2025 ISIS ARGUETA
Issued 10/31/2025 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 10/21/2025 GEVORK KARAPETYAN
Construction within easement Cleared 10/21/2025 GEVORK KARAPETYAN
Address approval Cleared 10/27/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 10/27/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 10/27/2025 SAFA JAVANMARDI
Sewer availability Cleared 10/27/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/1/2025 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 4/10/2026 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 4/15/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
METHANE-Barrier 4/15/2026 Approved ROBERTO PALACIOS-LOPEZ
METHANE-Subgrade 4/15/2026 Approved ROBERTO PALACIOS-LOPEZ
Sewer 4/15/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Sewer 4/20/2026 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/24/2026 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/4/2026 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 5/4/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 5/4/2026 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 5/4/2026 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Rough 5/4/2026 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/4/2026 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/11/2026 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 5/11/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 5/11/2026 Approved JENNIFER RABUCHIN
HVAC-Rough 5/11/2026 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/11/2026 Partial Approval JENNIFER RABUCHIN
MERV13>=Rough 5/11/2026 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/11/2026 Approved JENNIFER RABUCHIN
Insulation 5/18/2026 Corrections Issued MICHAEL CORTEZ
Shower Pan 5/18/2026 Approved MICHAEL CORTEZ
Drywall Nailing 5/20/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 5/20/2026 Approved JENNIFER RABUCHIN
Insulation 5/20/2026 Approved JENNIFER RABUCHIN