8208 N TEESDALE AVE 91605
Certificate Information: 8208 N TEESDALE AVE 91605
- Application / Permit
- 25014-20000-03969
- Plan Check / Job No.
- B25VN25590
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Conversion and addition to (E) detached garage to A.D.U. per LAMC 12.22 A.33 (b)(1). All work per WFPP.
- Permit Issued
- Issued on 11/20/2025
- Issuing Office
- Current Status
- Issued on 11/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2025 | GEORGE ALVAREZ |
| Corrections Issued | 9/11/2025 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 11/13/2025 | CAROLEAN BASMA |
| Plan Check Approved | 11/20/2025 | CAROLEAN BASMA |
| Issued | 11/20/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/17/2025 | SAFA JAVANMARDI |
| Address approval | Cleared | 9/17/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 9/17/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 9/22/2025 | SAFA JAVANMARDI |
| Construction near power lines | Cleared | 10/1/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/11/2026 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 3/16/2026 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 3/16/2026 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2026 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/22/2026 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Rough | 4/22/2026 | Approved | DAVID MATSON |
| Green Building Rough | 4/22/2026 | Not Ready for Inspection | DAVID MATSON |
| MERV13>=Rough | 4/22/2026 | Not Ready for Inspection | DAVID MATSON |
| PLUMBING-Rough | 4/22/2026 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 4/27/2026 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 4/27/2026 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/27/2026 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 4/30/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 4/30/2026 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/4/2026 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 5/4/2026 | Approved | JOSE AVILA |
| Drywall Nailing | 5/8/2026 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/12/2026 | Approved | OGANES TARAKHCHYAN |
| Final | 6/12/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 6/12/2026 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 6/12/2026 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Final | 6/12/2026 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Rough | 6/12/2026 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2026 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 6/12/2026 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 6/12/2026 | Approved | OGANES TARAKHCHYAN |