9542 N WOODMAN AVE 91331
Certificate Information: 9542 N WOODMAN AVE 91331
- Application / Permit
- 25014-20000-03949
- Plan Check / Job No.
- B25VN25452
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Addition to and conversion of (E) detached garage into an ADU per GC 66323(a)(2) and new pool bath
- Permit Issued
- Issued on 10/20/2025
- Issuing Office
- Current Status
- Issued on 10/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2025 | HOOMAN HAJIZADEH |
| Corrections Issued | 9/5/2025 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 10/3/2025 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 10/15/2025 | AMY GUEVARRA |
| Plan Check Approved | 10/20/2025 | AMY GUEVARRA |
| Issued | 10/20/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/17/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 9/17/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 9/17/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/18/2026 | No Access for Inspection | MICHEL ABAJAN |
| Pre-Inspection | 2/23/2026 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 3/16/2026 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 3/20/2026 | Approved | MICHEL ABAJAN |
| Sewer | 3/26/2026 | Approved | MICHEL ABAJAN |
| Sewer | 4/2/2026 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2026 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 4/20/2026 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/30/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 4/30/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Insulation | 5/4/2026 | Conditional Approval | MICHEL ABAJAN |