17531 W BLYTHE ST 91325
Certificate Information: 17531 W BLYTHE ST 91325
- Application / Permit
- 25014-20000-03937
- Plan Check / Job No.
- B25VN25401
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan PROPOSED AREA ADDITION (412 SF) INTO EXISTING 1-STORY SFD PROPOSED ATTACHED GARAGE TO BE CONVERTED INTO JADU
- Permit Issued
- Issued on 9/30/2025
- Issuing Office
- Current Status
- Issued on 9/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2025 | PINANK PATEL |
| Corrections Issued | 9/4/2025 | PINANK PATEL |
| Applicant returned to address corrections | 9/17/2025 | PINANK PATEL |
| Applicant returned to address corrections | 9/19/2025 | PINANK PATEL |
| Plan Check Approved | 9/30/2025 | PINANK PATEL |
| Issued | 9/30/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 9/11/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 9/11/2025 | SAFA JAVANMARDI |
| Address approval | Cleared | 9/16/2025 | JEREMY CHOK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
| Engineer | Zhong,, Raymond; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/8/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 10/10/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 10/10/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 10/10/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Sewer | 10/10/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 10/15/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 10/15/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Sewer | 10/15/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Green Building Rough | 10/17/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Sewer | 10/17/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 10/31/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 10/31/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Green Building Rough | 10/31/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| HVAC-Rough | 10/31/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 10/31/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 11/10/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 11/10/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 11/10/2025 | Conditional Approval | GAREN HAYRAPETYAN |
| Shower Pan | 11/10/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 11/19/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Gas Test | 11/19/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 11/19/2025 | Conditional Approval | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 11/19/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Shower Pan | 11/19/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 11/21/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Wood Frame | 11/21/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 11/26/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 11/26/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 11/26/2025 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 12/2/2025 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 12/2/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 12/19/2025 | Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 12/19/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Final | 6/4/2026 | Corrections Issued | MICHAEL CORTEZ |
| Green Building Final | 6/4/2026 | Corrections Issued | MICHAEL CORTEZ |
| SGSOV-Seismic Gas S/O Valve | 6/4/2026 | SGSOV Not Ready | MICHAEL CORTEZ |
| Smoke Detectors | 6/4/2026 | Corrections Issued | MICHAEL CORTEZ |