6507 N GENTRY AVE 91606

Certificate Information: 6507 N GENTRY AVE 91606

Application / Permit
25014-20000-03908
Plan Check / Job No.
B25VN25265
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. NEW ADDITION TO THE EXISTING SINGLE FAMILY DWELLING AND REMODEL. NEW ADDITION TO THE EXISTING PORCH.
Permit Issued
Issued on 10/6/2025
Issuing Office
Current Status
CofO Issued on 5/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2025 APPLICANT
Assigned to Plan Check Engineer 9/4/2025 MADISON ODELL
Corrections Issued 9/4/2025 MADISON ODELL
Applicant returned to address corrections 9/17/2025 MADISON ODELL
Plan Check Approved 10/3/2025 SARKIS HARABEDIAN
Issued 10/6/2025 APPLICANT
No Progress 4/10/2026 ROBERTO PALACIOS-LOPEZ
CofO in Progress 4/10/2026 ROBERTO PALACIOS-LOPEZ
CofO in Progress 4/18/2026 ROBERTO PALACIOS-LOPEZ
Permit Finaled 5/21/2026 RUBEN SALAS
CofO Issued 5/21/2026 RUBEN SALAS
Permit Finaled 5/21/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/16/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 9/19/2025 SAFA JAVANMARDI

Contact Information

Contractor United Builders & Development Inc; Lic. No.: 1066908-B       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/23/2025 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 10/28/2025 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/3/2025 Approved JOSE AVILA
PLUMBING-Rough 11/3/2025 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Approved JOSE AVILA
Insulation 11/7/2025 Partial Approval JOSE AVILA
ELECTRICAL-Rough 11/10/2025 Approved JOSE AVILA
PLUMBING-Rough 11/10/2025 Approved JOSE AVILA
Interior/Exterior Lathing 11/13/2025 Approved JOSE AVILA
Rough-Elec/Plmb/HVAC 11/13/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 11/17/2025 Approved JOSE AVILA
Insulation 11/17/2025 Approved JOSE AVILA
Interior/Exterior Lathing 11/17/2025 Approved JOSE AVILA
Shower Pan 11/17/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 12/9/2025 Approved JOSE AVILA
Final 12/9/2025 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 12/9/2025 Approved JOSE AVILA
Green Building Final 12/9/2025 Approved JOSE AVILA
Green Building Rough 12/9/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 12/9/2025 SGSOV Approved JOSE AVILA
Smoke Detectors 12/9/2025 Approved JOSE AVILA
Final 4/10/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ