7335 N KRAFT AVE 91605
Certificate Information: 7335 N KRAFT AVE 91605
- Application / Permit
- 25014-20000-03899
- Plan Check / Job No.
- B25VN25212
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: 637 SQFT ADDITION AND CONVERSION OF EXISTING 334 SQFT DETACHED GARAGE TO ADU PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k) , 1-STORY, NON SPRINKLERED
- Permit Issued
- Issued on 9/29/2025
- Issuing Office
- Current Status
- Issued on 9/29/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2025 | NGHI SU |
| Corrections Issued | 9/3/2025 | NGHI SU |
| Applicant returned to address corrections | 9/17/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 9/29/2025 | NGHI SU |
| Issued | 9/29/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/11/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 9/11/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 9/16/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/3/2025 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 12/15/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 12/15/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 12/22/2025 | Partial Approval | JOSE AVILA |
| Sewer | 12/22/2025 | Approved | JOSE AVILA |
| Pre-Inspection | 2/9/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Deputy Drilled-In Anchors | 2/10/2026 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 2/13/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 2/25/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 3/6/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 5/27/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 6/17/2026 | Partial Inspection | ROBERTO PALACIOS-LOPEZ |