7335 N KRAFT AVE 91605

Certificate Information: 7335 N KRAFT AVE 91605

Application / Permit
25014-20000-03899
Plan Check / Job No.
B25VN25212
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: 637 SQFT ADDITION AND CONVERSION OF EXISTING 334 SQFT DETACHED GARAGE TO ADU PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k) , 1-STORY, NON SPRINKLERED
Permit Issued
Issued on 9/29/2025
Issuing Office
Current Status
Issued on 9/29/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/28/2025 APPLICANT
Assigned to Plan Check Engineer 9/3/2025 NGHI SU
Corrections Issued 9/3/2025 NGHI SU
Applicant returned to address corrections 9/17/2025 NEHEMIAS RAMOS
Plan Check Approved 9/29/2025 NGHI SU
Issued 9/29/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/11/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 9/11/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/16/2025 MICHAEL BROWN
Sewer availability Cleared 9/16/2025 MICHAEL BROWN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/3/2025 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 12/15/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 12/15/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 12/22/2025 Partial Approval JOSE AVILA
Sewer 12/22/2025 Approved JOSE AVILA
Pre-Inspection 2/9/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 2/10/2026 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 2/13/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 2/25/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 3/6/2026 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/26/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 5/27/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 6/3/2026 Corrections Issued NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 6/5/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 6/17/2026 Partial Inspection ROBERTO PALACIOS-LOPEZ