6222-6224 N FALLBROOK AVE 91367

Certificate Information: 6222-6224 N FALLBROOK AVE 91367

Application / Permit
25014-20000-03893
Plan Check / Job No.
B25VN25161
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
Permit Issued
Issued on 9/18/2025
Issuing Office
Current Status
CofO Issued on 3/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2025 APPLICANT
Assigned to Plan Check Engineer 9/3/2025 GIOVANNY CHAVEZ
Corrections Issued 9/4/2025 GIOVANNY CHAVEZ
Applicant returned to address corrections 9/15/2025 GIOVANNY CHAVEZ
Plan Check Approved 9/18/2025 GIOVANNY CHAVEZ
Issued 9/18/2025 APPLICANT
CofO in Progress 3/6/2026 GEVORK IPCHYAN
Permit Finaled 3/20/2026 JOHN JANSON
CofO Issued 3/20/2026 JOHN JANSON
Permit Finaled 3/20/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/12/2025 TAL SHEMEN
Sewer availability Cleared 9/12/2025 TAL SHEMEN
ZA Case Cleared 9/12/2025 ROSALINDA MEZA
Eng Process Fee Ord 176,300 Cleared 9/15/2025 TAL SHEMEN
Grading Pre-Inspection Cleared 9/15/2025 GERMAN RODRIGUEZ MENDOZA

Contact Information

Contractor Owner-Builder       ,
Engineer De, Berardinis, Albert Francis; Lic. No.: C42010 504 THORN STREET UNIT 9      SAN DIEGO, CA 92103

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/17/2025 Conditional Approval GEVORK IPCHYAN
Excavation/Setback/Form/Re-Bar 10/24/2025 Not Ready for Inspection GEVORK IPCHYAN
ELECTRICAL-Rough 11/5/2025 Partial Approval SEAN WIRCH
Excavation/Setback/Form/Re-Bar 11/5/2025 Approved SEAN WIRCH
PLUMBING-Rough 11/5/2025 Partial Approval SEAN WIRCH
BUILDING-Rough-Frame 11/21/2025 Partial Approval GEVORK IPCHYAN
Green Building Rough 11/21/2025 Not Ready for Inspection GEVORK IPCHYAN
BUILDING-Rough-Frame 12/1/2025 Partial Approval GEVORK IPCHYAN
ELECTRICAL-Rough 12/1/2025 Partial Approval GEVORK IPCHYAN
Green Building Rough 12/1/2025 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Rough 12/1/2025 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 12/1/2025 Approved GEVORK IPCHYAN
Wood Frame 12/1/2025 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 12/16/2025 Approved GEVORK IPCHYAN
Drywall Nailing 12/16/2025 Approved GEVORK IPCHYAN
ELECTRICAL-Rough 12/16/2025 Approved GEVORK IPCHYAN
Gas Test 12/16/2025 Approved GEVORK IPCHYAN
Green Building Rough 12/16/2025 Approved GEVORK IPCHYAN
HVAC-Rough 12/16/2025 Approved GEVORK IPCHYAN
Insulation 12/16/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 12/16/2025 Partial Approval GEVORK IPCHYAN
Shower Pan 12/16/2025 Approved GEVORK IPCHYAN
Final 1/16/2026 Not Ready for Inspection GEVORK IPCHYAN
Green Building Final 1/16/2026 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 1/16/2026 SGSOV Not Ready GEVORK IPCHYAN
Smoke Detectors 1/16/2026 Not Ready for Inspection GEVORK IPCHYAN
ELECTRICAL-Final 3/6/2026 Approved GEVORK IPCHYAN
Final 3/6/2026 OK to Issue CofO GEVORK IPCHYAN
Green Building Final 3/6/2026 Approved GEVORK IPCHYAN
HVAC-Final 3/6/2026 Approved GEVORK IPCHYAN
PLUMBING-Final 3/6/2026 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 3/6/2026 SGSOV Approved GEVORK IPCHYAN
Smoke Detectors 3/6/2026 Approved GEVORK IPCHYAN