10851-10855 N SHARP AVE 91345

Certificate Information: 10851-10855 N SHARP AVE 91345

Application / Permit
25014-20000-03876
Plan Check / Job No.
B25VN25044
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL TO (E) SFD, ADDITION OF A BREEZEWAY ATTACHED TO A (N) 1-STORY ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c) and (e) AND CONVERT (E) ATTACHED GARAGE WITH ADDITIONS TO CREATE A (N) JUNIOR ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 66323(a)(1) AND 66333
Permit Issued
Issued on 12/22/2025
Issuing Office
Current Status
Issued on 12/22/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/27/2025 APPLICANT
Assigned to Plan Check Engineer 8/28/2025 ALFRED RAMIREZ
Corrections Issued 8/30/2025 ALFRED RAMIREZ
Quality Review Completed 9/4/2025 STEVEN KIM
Building Plans Picked Up 9/5/2025 APPLICANT
Assigned to Zoning Architect 11/5/2025 ELAHE MERRIKHI
Plan Check Approved 12/22/2025 ALFRED RAMIREZ
Issued 12/22/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/17/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/17/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/17/2025 LEE GUILBEAUX
Sewer availability Cleared 9/17/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/17/2025 LEE GUILBEAUX
"Q" conditions Cleared 12/3/2025 DORIAN AGUILAR
"T" removal Cleared 12/3/2025 DORIAN AGUILAR
Miscellaneous Cleared 12/3/2025 DORIAN AGUILAR
Zoning Plan Check Cleared 12/11/2025 ELAHE MERRIKHI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/6/2026 Partial Approval JENNIFER RABUCHIN
METHANE-Barrier 2/6/2026 Approved JENNIFER RABUCHIN
METHANE-Subgrade 2/6/2026 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/2/2026 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 3/2/2026 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/6/2026 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 3/6/2026 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/16/2026 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 3/16/2026 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/24/2026 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/8/2026 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 4/13/2026 Approved JENNIFER RABUCHIN
Deputy Drilled-In Anchors 4/20/2026 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 4/23/2026 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 4/23/2026 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 4/23/2026 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 5/1/2026 Approved JENNIFER RABUCHIN
HVAC-Rough 5/1/2026 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/1/2026 Partial Approval JENNIFER RABUCHIN
Insulation 5/11/2026 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/11/2026 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 5/19/2026 Approved JENNIFER RABUCHIN
Green Building Rough 5/19/2026 Approved JENNIFER RABUCHIN