5719 N RANCHITO AVE 91401
Certificate Information: 5719 N RANCHITO AVE 91401
- Application / Permit
- 25014-20000-03845
- Plan Check / Job No.
- B25VN24823
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: ADDITION AND CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(2)
- Permit Issued
- Issued on 9/9/2025
- Issuing Office
- Current Status
- CofO in Progress on 3/12/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2025 | DANIEL YIP |
| Corrections Issued | 8/29/2025 | DANIEL YIP |
| Plan Check Approved | 9/9/2025 | DANIEL YIP |
| Issued | 9/9/2025 | APPLICANT |
| CofO in Progress | 3/12/2026 | VINCENT HANLEY |
Permit Application Clearance Information
| Address approval | Cleared | 9/2/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 9/2/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/4/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/4/2025 | BIAINA HARITUNIAN |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/15/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2025 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/12/2025 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 11/12/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 11/12/2025 | Approved | RYAN SALAZAR |
| Wood Frame | 11/12/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/17/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 11/17/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Rough-Elec/Plmb/HVAC | 11/17/2025 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 11/19/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 11/21/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 11/21/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/24/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 11/25/2025 | Approved | RYAN SALAZAR |
| Sewer | 1/21/2026 | Approved | RYAN SALAZAR |
| Sewer | 1/26/2026 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 1/26/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Sewer | 1/30/2026 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 1/30/2026 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 2/13/2026 | Approved | VINCENT HANLEY |
| Final | 2/13/2026 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 2/13/2026 | Approved | VINCENT HANLEY |
| HVAC-Final | 2/13/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 2/13/2026 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/13/2026 | SGSOV Not Ready | VINCENT HANLEY |
| Smoke Detectors | 2/13/2026 | Approved | VINCENT HANLEY |
| Final | 2/24/2026 | Not Ready for Inspection | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 2/24/2026 | SGSOV Not Ready | DAVID MATSON |
| Final | 3/6/2026 | Conditional Approval | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 3/6/2026 | SGSOV Approved | DAVID MATSON |
| Final | 3/12/2026 | OK to Issue CofO | VINCENT HANLEY |
| PLUMBING-Final | 3/12/2026 | Approved | VINCENT HANLEY |