4319 N BABCOCK AVE 91604

Certificate Information: 4319 N BABCOCK AVE 91604

Application / Permit
25014-20000-03831
Plan Check / Job No.
B25VN24731
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 12' X 18'-10" DETACHED GARAGE AND 12'-11" X 36'-9" ADD FOR (N) ADU PER LAMC 12.22 A.33(b)(1). NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER WFPP.
Permit Issued
Issued on 11/13/2025
Issuing Office
Valley
Current Status
Issued on 11/13/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/25/2025 APPLICANT
Assigned to Plan Check Engineer 8/28/2025 RAPHAEL ROSAS
Assigned to Zoning Architect 8/28/2025 MEGAN KOLP
Corrections Issued 9/10/2025 RAPHAEL ROSAS
Quality Review Completed 9/12/2025 STEVEN KIM
Building Plans Picked Up 9/16/2025 APPLICANT
Applicant returned to address corrections 10/31/2025 RAPHAEL ROSAS
Applicant returned to address corrections 11/4/2025 RAPHAEL ROSAS
Plan Check Approved 11/13/2025 RAPHAEL ROSAS
Issued 11/13/2025 APPLICANT

Permit Application Clearance Information

Low Impact Development (LID) Cleared 9/10/2025 ERNEST TSE
Address approval Cleared 10/1/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/1/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 10/1/2025 CINDY QI
Sewer availability Cleared 10/1/2025 BIAINA HARITUNIAN
ZI Cleared 10/1/2025 BRENNEN OBETO
Construction near power lines Cleared 10/21/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/23/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 12/23/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 1/16/2026 Corrections Issued CHRISTOPHE COCHRAN
Underground Mechanical 1/21/2026 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 1/29/2026 Corrections Issued MISAEL ESPARZA
Pre-Inspection 1/29/2026 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 2/3/2026 Partial Approval CHRISTOPHE COCHRAN
Deputy Steel/Welding 2/23/2026 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 3/24/2026 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/24/2026 Partial Approval JAVIER RAMOS JR
Pre-Inspection 3/24/2026 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 4/23/2026 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 4/23/2026 Approved CHRISTOPHE COCHRAN
Green Building Rough 4/23/2026 Approved CHRISTOPHE COCHRAN
HVAC-Rough 4/23/2026 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 4/23/2026 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 4/30/2026 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 5/14/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Wood Frame 5/14/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 5/20/2026 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 5/20/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 5/20/2026 Approved ROBERTO PALACIOS-LOPEZ
Insulation 6/5/2026 Approved CHRISTOPHE COCHRAN
Drywall Nailing 6/18/2026 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/18/2026 Approved CHRISTOPHE COCHRAN
Pre-Inspection 6/18/2026 Approved CHRISTOPHE COCHRAN
Shower Pan 6/18/2026 Approved CHRISTOPHE COCHRAN