ePlan. NEW IRREGULAR-SHAPED 40'-1" X 25'-7" ADDITION TO EXISTING 363 SF DETACHED GARAGE AND CONVERSION INTO AN ADU PER LAMC 12.22A.33. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/25/2025
Issuing Office
Current Status
Issued on 10/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/25/2025 APPLICANT
Assigned to Plan Check Engineer 8/28/2025 EDWIN MARTINEZ
Corrections Issued 8/29/2025 EDWIN MARTINEZ
Plan Check Approved 10/20/2025 CRYSTEL MAALOUF
Issued 10/25/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/2/2025 MANUEL TEJADA
Address approval Cleared 9/5/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 9/5/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 9/8/2025 SAFA JAVANMARDI
Sewer availability Cleared 9/15/2025 SAFA JAVANMARDI
Construction near power lines Cleared 10/1/2025 GEVORK KARAPETYAN
GPI Written Notices Cleared 10/20/2025 GERMAN RODRIGUEZ MENDOZA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/16/2026 Approved CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 2/6/2026 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 2/9/2026 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 2/9/2026 Partial Approval CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 2/13/2026 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 2/13/2026 Approved CHRISTOPHER ROJAS
Deputy Wood Construction 3/19/2026 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/23/2026 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 4/8/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 4/8/2026 Approved CHRISTOPHER ROJAS
Gas Test 4/8/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 4/8/2026 Approved CHRISTOPHER ROJAS
HVAC-Rough 4/8/2026 Approved CHRISTOPHER ROJAS
MERV13>=Rough 4/8/2026 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 4/8/2026 Approved CHRISTOPHER ROJAS
Insulation 4/22/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/22/2026 Partial Approval CHRISTOPHER ROJAS
Drywall Nailing 4/30/2026 Approved CHRISTOPHER ROJAS
Shower Pan 5/27/2026 Approved CHRISTOPHER ROJAS