14500 W HERRON ST 91342

Certificate Information: 14500 W HERRON ST 91342

Application / Permit
25014-20000-03807
Plan Check / Job No.
B25VN24580
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REFRAME (E) RR AND CJ DAMAGED BY FIRE AND INTERIOR REMODEL AND . 26'-6"x5'-6" ONE STORY ADDITION. ALL WORK PER ENGINEERING
Permit Issued
Issued on 9/8/2025
Issuing Office
Valley
Current Status
CofO Issued on 2/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2025 APPLICANT
Assigned to Plan Check Engineer 8/28/2025 JESSE ARELLANO
Corrections Issued 8/29/2025 JESSE ARELLANO
Building Plans Picked Up 9/2/2025 APPLICANT
Issued 9/8/2025 APPLICANT
CofO in Progress 12/2/2025 JENNIFER RABUCHIN
Permit Finaled 2/14/2026 MICHAEL PELHAM
CofO Issued 2/14/2026 MICHAEL PELHAM
Permit Finaled 2/14/2026 MICHAEL PELHAM

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/3/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/3/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/3/2025 LEE GUILBEAUX

Contact Information

Contractor Vicsinc.Com; Lic. No.: 1002544-B P O BOX 950931      MISSION HILLS, CA 91395
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/10/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 9/10/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/1/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/1/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 10/1/2025 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 10/1/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 10/1/2025 Approved JENNIFER RABUCHIN
Wood Frame 10/1/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/3/2025 Approved JENNIFER RABUCHIN
Shower Pan 10/3/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 10/9/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/26/2025 Approved JENNIFER RABUCHIN
Final 11/26/2025 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 11/26/2025 Approved JENNIFER RABUCHIN
Green Building Rough 11/26/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/26/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 11/26/2025 Approved JENNIFER RABUCHIN