7934 N NITA AVE 91304

Certificate Information: 7934 N NITA AVE 91304

Application / Permit
25014-20000-03784
Plan Check / Job No.
B25VN24453
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: 1-Story Addition at rear of (E) Single Family Dwelling . **NFPA 13D Fire Sprinklers Thru-Out**
Permit Issued
Issued on 9/19/2025
Issuing Office
Current Status
Issued on 9/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/21/2025 APPLICANT
Assigned to Plan Check Engineer 8/26/2025 ZAW HAN
Corrections Issued 8/27/2025 ZAW HAN
Applicant returned to address corrections 9/16/2025 GEORGE ALVAREZ
Plan Check Approved 9/19/2025 CARLOS MONTES
Issued 9/19/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/8/2025 TAL SHEMEN
Sewer availability Cleared 9/8/2025 TAL SHEMEN
Roof/Waste drainage to street Cleared 9/16/2025 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: NA93079       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/27/2025 Partial Approval JEFFREY HARTLINE
Deputy Drilled-In Anchors 12/17/2025 Conditional Approval HENRY KIM
Excavation/Setback/Form/Re-Bar 12/17/2025 Corrections Issued JEFFREY HARTLINE
Footing/Foundation/Slab 12/17/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 1/9/2026 Partial Approval JEFFREY HARTLINE
Green Building Rough 1/9/2026 Not Ready for Inspection JEFFREY HARTLINE
PLUMBING-Rough 1/9/2026 Partial Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 1/15/2026 Partial Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 4/3/2026 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 4/9/2026 Partial Approval JEFFREY HARTLINE
Green Building Rough 4/9/2026 Approved JEFFREY HARTLINE
Rough-Elec/Plmb/HVAC 4/9/2026 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 4/9/2026 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 4/21/2026 Approved JEFFREY HARTLINE
Insulation 4/21/2026 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 4/21/2026 Partial Approval JEFFREY HARTLINE
Drywall Nailing 5/8/2026 Approved JEFFREY HARTLINE
Shower Pan 5/8/2026 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 5/18/2026 No Access for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 5/19/2026 Approved JEFFREY HARTLINE