15546-15548 W OLDEN ST 91342

Certificate Information: 15546-15548 W OLDEN ST 91342

Application / Permit
25014-20000-03710
Plan Check / Job No.
B25VN23867
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition (28 SF) and Conversion (E) Attached Garage (369 SF) to attached ADU, Convert (E) SFD (141SF) convert to part of new ADU per GC & 66323(A) (1). See Comment.
Permit Issued
Issued on 9/22/2025
Issuing Office
Current Status
CofO in Progress on 4/1/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/19/2025 APPLICANT
Assigned to Plan Check Engineer 8/22/2025 SUNMIN LEE
Corrections Issued 8/26/2025 TSE MING HUANG
Corrections Issued 9/4/2025 SUNMIN LEE
Applicant returned to address corrections 9/11/2025 DANIEL SMILEY
Applicant returned to address corrections 9/13/2025 TSE MING HUANG
Plan Check Approved 9/22/2025 TSE MING HUANG
Issued 9/22/2025 APPLICANT
CofO in Progress 4/1/2026 KEVIN BERBERYAN

Permit Application Clearance Information

Address approval Cleared 8/31/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 9/4/2025 DERRICK MAGEE
Sewer availability Cleared 9/4/2025 DERRICK MAGEE
Grading Pre-Inspection Cleared 9/16/2025 TSE MING HUANG
Zoning Information File Cleared 9/22/2025 TSE MING HUANG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/7/2025 Partial Approval KEVIN BERBERYAN
Deputy Drilled-In Anchors 11/12/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 11/13/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 12/8/2025 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 12/8/2025 Approved KEVIN BERBERYAN
HVAC-Rough 12/8/2025 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 12/8/2025 Approved KEVIN BERBERYAN
Insulation 1/7/2026 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 1/7/2026 Partial Approval OGANES TARAKHCHYAN
Drywall Nailing 1/9/2026 Approved KEVIN BERBERYAN
Green Building Rough 1/9/2026 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 2/4/2026 Approved KEVIN BERBERYAN
Service/Power Release 2/4/2026 Corrections Issued KEVIN BERBERYAN
Sewer 2/9/2026 Approved KIRK SANDERS
Underground Mechanical 2/9/2026 Approved KIRK SANDERS
Gas Test 2/13/2026 Approved KEVIN BERBERYAN
Service/Power Release 2/13/2026 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 2/26/2026 Approved KEVIN BERBERYAN
Final 2/26/2026 Partial Approval KEVIN BERBERYAN
Green Building Final 2/26/2026 Approved KEVIN BERBERYAN
MERV13>=Final 2/26/2026 Approved KEVIN BERBERYAN
MERV13>=Rough 2/26/2026 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 2/26/2026 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 2/26/2026 Approved KEVIN BERBERYAN
Final 4/1/2026 OK to Issue CofO KEVIN BERBERYAN