7251 N BERNADINE AVE 91307
Certificate Information: 7251 N BERNADINE AVE 91307
- Application / Permit
- 25014-20000-03692
- Plan Check / Job No.
- B25VN23727
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL TO SFD
- Permit Issued
- Issued on 9/18/2025
- Issuing Office
- Current Status
- Issued on 9/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2025 | SELLA BENYAMIN |
| Corrections Issued | 8/26/2025 | SELLA BENYAMIN |
| Quality Review Completed | 9/2/2025 | STEVEN KIM |
| Building Plans Picked Up | 9/2/2025 | APPLICANT |
| Plan Check Approved | 9/18/2025 | SELLA BENYAMIN |
| Issued | 9/18/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/26/2025 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 8/26/2025 | ADRIAN SANCHEZ |
| Grading Pre-Inspection | Cleared | 8/26/2025 | ALEXANDER HELFER |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2025 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/27/2025 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 10/30/2025 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 11/4/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Steel/Welding | 12/9/2025 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Partial Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 12/18/2025 | Approved | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 1/21/2026 | Conditional Approval | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 1/29/2026 | Corrections Issued | DAVID FASTIGGI |
| ELECTRICAL-Rough | 2/3/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 2/3/2026 | Partial Approval | JEFFREY HARTLINE |
| PLUMBING-Rough | 2/3/2026 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 2/10/2026 | Corrections Issued | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 2/10/2026 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 2/10/2026 | Approved | JEFFREY HARTLINE |
| Shower Pan | 2/10/2026 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 2/23/2026 | Approved | JEFFREY HARTLINE |
| Insulation | 2/23/2026 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 3/11/2026 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 3/19/2026 | Approved | JEFFREY HARTLINE |