125 S LARCHMONT BLVD 90004
Certificate Information: 125 S LARCHMONT BLVD 90004
- Application / Permit
- 25014-20000-03677
- Plan Check / Job No.
- B25VN23628
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE ALL BUT 18'-5" LF OF WALL AND REBUILD IRREG SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/26/2025
- Issuing Office
- Metro
- Current Status
- Issued on 11/26/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 8/22/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 8/26/2025 | APPLICANT |
| Applicant returned to address corrections | 10/31/2025 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 11/17/2025 | OMAR GARNICA |
| Issued | 11/26/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/4/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 9/4/2025 | MICHAEL BROWN |
| HPOZ | Cleared | 9/4/2025 | DAMIAN GATTO |
| Roof/Waste drainage to street | Cleared | 9/4/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 9/4/2025 | MICHAEL BROWN |
| Construction near power lines | Cleared | 9/15/2025 | ENRIQUE ACOSTA |
Contact Information
| Contractor | Omni Company The; Lic. No.: 1078616-B | 12112 LOUIS AVE WHITTIER, CA 90605 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 1038 FLANDERS RD LA CANADA-FLNTRDG, CA 91011 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/17/2025 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 12/19/2025 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 12/22/2025 | Partial Approval | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 12/30/2025 | Approved | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 1/2/2026 | Approved | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 2/2/2026 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 2/2/2026 | Approved | RONNIE MINDANAO |
| METHANE-Barrier | 2/2/2026 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 2/2/2026 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2026 | Partial Approval | JOSH MEISTER |
| BUILDING-Rough-Frame | 4/22/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 4/22/2026 | Corrections Issued | RONNIE MINDANAO |
| Green Building Rough | 4/22/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 4/22/2026 | Approved | RONNIE MINDANAO |
| METHANE-Rough | 4/22/2026 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 4/22/2026 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 5/5/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 5/5/2026 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2026 | Approved | RONNIE MINDANAO |
| Green Building Rough | 5/5/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 5/14/2026 | Approved Pending GreenApproval | RONNIE MINDANAO |
| Green Building Rough | 5/14/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 5/14/2026 | Approved | RONNIE MINDANAO |
| Insulation | 5/20/2026 | Corrections Issued | RONNIE MINDANAO |
| Shower Pan | 5/20/2026 | Approved | RONNIE MINDANAO |
| Insulation | 5/22/2026 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 5/29/2026 | Approved | JOSH MEISTER |
| Sewer | 7/13/2026 | Not Ready for Inspection | RONNIE MINDANAO |