13449 W STAGG ST 91402
Certificate Information: 13449 W STAGG ST 91402
- Application / Permit
- 25014-20000-03660
- Plan Check / Job No.
- B25VN23501
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (E) SFD, ENCLOSE 6'-10" X 6'-0" PORCH, 7'-10" X 4'-3" PORCH ADDITION & 44'-11" X 12'-10" IRREGULAR SHAPED ADDITION TO (E) SFD.
- Permit Issued
- Issued on 8/29/2025
- Issuing Office
- Current Status
- CofO Issued on 2/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 8/21/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 8/22/2025 | APPLICANT |
| Plan Check Approved | 8/29/2025 | NAREG ATARIAN |
| Issued | 8/29/2025 | APPLICANT |
| CofO in Progress | 1/26/2026 | VINCENT HANLEY |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
| CofO Issued | 2/12/2026 | RUBEN SALAS |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 8/22/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 8/22/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mosesian,, Peter; Lic. No.: C95745 | 86 SMOKE TREE AVE OAK PARK, CA 91377 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/23/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/2/2025 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 10/2/2025 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 10/2/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2025 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/23/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 10/23/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 10/23/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/3/2025 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 11/3/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 11/12/2025 | Partial Approval | LOUIS ESCOTO |
| Insulation | 11/17/2025 | Approved | CHRISTOPHER MORFIN |
| Shower Pan | 11/17/2025 | Not Ready for Inspection | CHRISTOPHER MORFIN |
| Shower Pan | 11/18/2025 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 11/26/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 1/23/2026 | Approved | VINCENT HANLEY |
| Final | 1/23/2026 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 1/23/2026 | Approved | VINCENT HANLEY |
| HVAC-Final | 1/23/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 1/23/2026 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 1/23/2026 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 1/23/2026 | Approved | VINCENT HANLEY |
| Smoke Detectors | 1/23/2026 | Approved | VINCENT HANLEY |