601 S WARNER AVE 90024

Certificate Information: 601 S WARNER AVE 90024

Application / Permit
25014-20000-03657
Plan Check / Job No.
B25VN23497
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, CONVERT (19' X 6') PORTION OF GARAGE TO HABITABLE SPACE AND (7' X 5'-6"), (37' X 4'-8") ADDITIONS TO THE EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 10/28/2025
Issuing Office
Valley
Current Status
Issued on 10/28/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/13/2025 APPLICANT
Assigned to Plan Check Engineer 9/4/2025 VAHAN JIVALAGIAN
Corrections Issued 9/6/2025 VAHAN JIVALAGIAN
Quality Review Completed 9/8/2025 OMID HEDAYAT
Building Plans Picked Up 9/15/2025 APPLICANT
Applicant returned to address corrections 10/22/2025 VAHAN JIVALAGIAN
Plan Check Approved 10/28/2025 VAHAN JIVALAGIAN
Issued 10/28/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/6/2025 VAHAN JIVALAGIAN
Specific Plan Cleared 10/7/2025 EDER ROMERO
Eng Process Fee Ord 176,300 Cleared 10/8/2025 JESUS CISNEROS
Roof/Waste drainage to street Cleared 10/8/2025 JESUS CISNEROS
Sewer availability Cleared 10/8/2025 JESUS CISNEROS

Contact Information

Contractor Construction Masters; Lic. No.: 762655-B 18075 VENTURA BLVD STE 135      ENCINO, CA 91316
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/15/2025 Not Ready for Inspection DANIEL VERA
Deputy Drilled-In Anchors 12/16/2025 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 12/18/2025 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 12/23/2025 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 1/7/2026 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 1/9/2026 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 3/6/2026 Partial Approval EVAN COOPER
Green Building Rough 3/6/2026 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 3/6/2026 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 3/12/2026 Not Ready for Inspection RYAN SALAZAR
Interior/Exterior Lathing 3/12/2026 Approved RYAN SALAZAR
PLUMBING-Rough 3/12/2026 Approved RYAN SALAZAR
BUILDING-Rough-Frame 3/19/2026 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 3/19/2026 Approved CARLOS MATAMOROS
HVAC-Rough 3/19/2026 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 3/25/2026 Approved CARLOS MATAMOROS
Green Building Rough 3/25/2026 Approved CARLOS MATAMOROS
Insulation 3/25/2026 Approved CARLOS MATAMOROS
Drywall Nailing 4/22/2026 Approved CARLOS MATAMOROS