9517 N COMANCHE AVE 91311

Certificate Information: 9517 N COMANCHE AVE 91311

Application / Permit
25014-20000-03603
Plan Check / Job No.
B25VN23102
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Addition to dwelling to enlarge family room and create additional bedroom. Patio addition to rear of dwelling.
Permit Issued
Issued on 9/15/2025
Issuing Office
Current Status
CofO in Progress on 2/23/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/11/2025 APPLICANT
Assigned to Plan Check Engineer 8/15/2025 RICARDO RAMIREZ
Corrections Issued 8/18/2025 RICARDO RAMIREZ
Applicant returned to address corrections 8/26/2025 NGHI SU
Plan Check Approved 9/12/2025 NGHI SU
Issued 9/15/2025 APPLICANT
CofO in Progress 2/23/2026 DAVID SCANTLIN

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/22/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 8/25/2025 SAFA JAVANMARDI
Sewer availability Cleared 8/25/2025 SAFA JAVANMARDI

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Preferred Home Builders Inc; Lic. No.: 773147-B       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/4/2025 Conditional Approval DAVID SCANTLIN
Deputy Drilled-In Anchors 11/6/2025 Conditional Approval DAVID SCANTLIN
Footing/Foundation/Slab 11/10/2025 Approved KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 12/9/2025 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 12/15/2025 Conditional Approval KRISTEN CAUSEY
ELECTRICAL-Rough 12/15/2025 Approved KRISTEN CAUSEY
Green Building Rough 12/15/2025 Approved KRISTEN CAUSEY
HVAC-Rough 12/15/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 12/15/2025 Partial Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 12/18/2025 Approved HENRY KIM
Insulation 12/18/2025 Approved HENRY KIM
Drywall Nailing 12/30/2025 Approved DAVID SCANTLIN
Final 2/13/2026 Partial Inspection ROBERT GOLD
Green Building Final 2/13/2026 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 2/13/2026 SGSOV Approved ROBERT GOLD
Smoke Detectors 2/13/2026 Corrections Issued ROBERT GOLD
Final 2/20/2026 OK to Issue CofO DAVID SCANTLIN
Smoke Detectors 2/20/2026 Approved DAVID SCANTLIN
Special/Order Compliance 3/2/2026 Corrections Issued DAVID SCANTLIN