7825 N NITA AVE 91304
Certificate Information: 7825 N NITA AVE 91304
- Application / Permit
- 25014-20000-03588
- Plan Check / Job No.
- B25VN22974
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEWREAR ADDITION TO (E) SFD, ALL WORK PER ENG.
- Permit Issued
- Issued on 9/2/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2025 | LUISANGEL VALENZUELA |
| Corrections Issued | 8/16/2025 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 8/19/2025 | APPLICANT |
| Issued | 9/2/2025 | APPLICANT |
| CofO in Progress | 2/12/2026 | CHRIS CHRISTENSEN |
| Permit Finaled | 3/3/2026 | JOHN JANSON |
| CofO Issued | 3/3/2026 | JOHN JANSON |
| Permit Finaled | 3/3/2026 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/21/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/22/2025 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2025 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 10/15/2025 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/24/2025 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 10/24/2025 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 10/24/2025 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 10/24/2025 | Approved | CHRIS CHRISTENSEN |
| Insulation | 10/28/2025 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 11/3/2025 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 1/21/2026 | Approved | CHRIS CHRISTENSEN |
| Final | 1/21/2026 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 1/21/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Final | 1/21/2026 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 1/21/2026 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 1/21/2026 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 1/21/2026 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 2/11/2026 | Approved | CHRIS CHRISTENSEN |
| Final | 2/11/2026 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 2/11/2026 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 2/11/2026 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 2/11/2026 | Partial Approval | CHRIS CHRISTENSEN |