10107-10111 N BURNET AVE 91345
Certificate Information: 10107-10111 N BURNET AVE 91345
- Application / Permit
- 25014-20000-03585
- Plan Check / Job No.
- B25VN22966
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AND CONVERT (E) ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT (432 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 8/22/2025
- Issuing Office
- Current Status
- CofO Issued on 1/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 8/19/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 8/20/2025 | APPLICANT |
| Issued | 8/22/2025 | APPLICANT |
| CofO in Progress | 1/13/2026 | JENNIFER RABUCHIN |
| Permit Finaled | 1/28/2026 | RUBEN SALAS |
| CofO Issued | 1/28/2026 | RUBEN SALAS |
| Permit Finaled | 1/28/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/20/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2025 | CINDY QI |
| Sewer availability | Cleared | 8/21/2025 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/3/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/3/2025 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/16/2025 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/16/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 10/16/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 10/16/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/16/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/21/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/21/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 10/21/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/21/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/21/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/21/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 10/23/2025 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 10/28/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 10/30/2025 | Approved | CHRISTOPHER MORFIN |
| Final | 1/7/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/7/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/7/2026 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 1/7/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/13/2026 | Approved | JENNIFER RABUCHIN |
| Final | 1/13/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 1/13/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/13/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/13/2026 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 1/13/2026 | Approved | JENNIFER RABUCHIN |