10107-10111 N BURNET AVE 91345

Certificate Information: 10107-10111 N BURNET AVE 91345

Application / Permit
25014-20000-03585
Plan Check / Job No.
B25VN22966
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERT (E) ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT (432 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 8/22/2025
Issuing Office
Current Status
CofO Issued on 1/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/8/2025 APPLICANT
Assigned to Plan Check Engineer 8/15/2025 JEROME MAGAT PALMA
Corrections Issued 8/19/2025 JEROME MAGAT PALMA
Building Plans Picked Up 8/20/2025 APPLICANT
Issued 8/22/2025 APPLICANT
CofO in Progress 1/13/2026 JENNIFER RABUCHIN
Permit Finaled 1/28/2026 RUBEN SALAS
CofO Issued 1/28/2026 RUBEN SALAS
Permit Finaled 1/28/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/20/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 8/21/2025 CINDY QI
Sewer availability Cleared 8/21/2025 CINDY QI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/3/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 10/3/2025 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/16/2025 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 10/16/2025 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/16/2025 Approved JENNIFER RABUCHIN
Green Building Rough 10/16/2025 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 10/16/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 10/16/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/21/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/21/2025 Approved JENNIFER RABUCHIN
Green Building Rough 10/21/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 10/21/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/21/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 10/21/2025 Approved JENNIFER RABUCHIN
Insulation 10/23/2025 Approved MICHAEL CORTEZ
Drywall Nailing 10/28/2025 Approved JENNIFER RABUCHIN
Shower Pan 10/30/2025 Approved CHRISTOPHER MORFIN
Final 1/7/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/7/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/7/2026 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 1/7/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 1/13/2026 Approved JENNIFER RABUCHIN
Final 1/13/2026 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 1/13/2026 Approved JENNIFER RABUCHIN
PLUMBING-Final 1/13/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/13/2026 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 1/13/2026 Approved JENNIFER RABUCHIN