8127-8129 N NATICK AVE 91402

Certificate Information: 8127-8129 N NATICK AVE 91402

Application / Permit
25014-20000-03574
Plan Check / Job No.
B25VN22915
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. Convert (E) attached garage to an Accessory Dwelling Unit w/ addition per GC 66323(a)(1)
Permit Issued
Issued on 11/17/2025
Issuing Office
Current Status
CofO Issued on 6/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2025 APPLICANT
Assigned to Plan Check Engineer 8/18/2025 AMY GUEVARRA
Corrections Issued 8/21/2025 AMY GUEVARRA
Applicant returned to address corrections 10/6/2025 AMY GUEVARRA
Plan Check Approved 11/4/2025 AMY GUEVARRA
Issued 11/17/2025 APPLICANT
CofO in Progress 6/11/2026 OGANES TARAKHCHYAN
CofO Issued 6/17/2026 RUBEN SALAS
Permit Finaled 6/17/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/2/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 9/4/2025 CINDY QI
Sewer availability Cleared 9/4/2025 CINDY QI
Roof/Waste drainage to street Cleared 10/3/2025 CINDY QI

Contact Information

Contractor Owner-Builder       ,
Engineer Crook,, Barrett Cameron; Lic. No.: C57196 5306 MULHOLLAND DRIVE      SUMMERVILLE, SC 29485

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/4/2025 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/9/2025 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 12/23/2025 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/6/2026 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 1/6/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 1/6/2026 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 1/6/2026 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/13/2026 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 1/13/2026 Approved OGANES TARAKHCHYAN
Gas Test 1/13/2026 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 1/13/2026 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 1/13/2026 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 1/13/2026 Approved OGANES TARAKHCHYAN
Insulation 1/21/2026 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/26/2026 Approved VINCENT HANLEY
Green Building Rough 1/26/2026 Approved VINCENT HANLEY
Insulation 1/26/2026 Approved VINCENT HANLEY
Drywall Nailing 1/29/2026 Approved OGANES TARAKHCHYAN
Shower Pan 2/9/2026 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/12/2026 Approved OGANES TARAKHCHYAN
Final 4/28/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 4/28/2026 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/28/2026 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 4/28/2026 Approved OGANES TARAKHCHYAN
Final 6/1/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 6/1/2026 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 6/1/2026 SGSOV Approved OGANES TARAKHCHYAN
Final 6/5/2026 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 6/5/2026 Approved OGANES TARAKHCHYAN