7021-7023 N INDEPENDENCE AVE 91303
Certificate Information: 7021-7023 N INDEPENDENCE AVE 91303
- Application / Permit
- 25014-20000-03563
- Plan Check / Job No.
- B25VN22830
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN: MAJOR REMODEL AND ADDITION TO CONVERT (E) SFD TO DUPLEX PER SB9. FIRE SPRINKLERE THROUGH OUT
- Permit Issued
- Issued on 11/10/2025
- Issuing Office
- Current Status
- Issued on 11/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2025 | VARAND SARKISIAN |
| Corrections Issued | 8/17/2025 | VARAND SARKISIAN |
| Quality Review Completed | 8/20/2025 | GARO TELMI |
| Applicant returned to address corrections | 10/1/2025 | VARAND SARKISIAN |
| Applicant returned to address corrections | 10/23/2025 | VARAND SARKISIAN |
| Plan Check Approved | 11/4/2025 | VARAND SARKISIAN |
| Issued | 11/10/2025 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 8/27/2025 | LAVEON RIDER |
| Address approval | Cleared | 9/4/2025 | LEE GUILBEAUX |
| Permit | Cleared | 9/4/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 9/4/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 9/4/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/9/2025 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 9/23/2025 | ERNEST TSE |
| Trees in Parkway | Cleared | 10/3/2025 | RICHARD SANCHEZ |
| Senate Bill 9 | Cleared | 10/6/2025 | DANIEL CORONADO |
| ZI | Cleared | 10/6/2025 | DANIEL CORONADO |
Contact Information
| Contractor | Pnr Builders Inc; Lic. No.: 1028148-B | , |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/18/2025 | Partial Approval | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 12/22/2025 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 3/20/2026 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 3/20/2026 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 3/20/2026 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2026 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 4/6/2026 | Approved | DAVID FASTIGGI |
| ELECTRICAL-Rough | 4/13/2026 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 4/13/2026 | Conditional Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 4/13/2026 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 4/16/2026 | Corrections Issued | ALEXANDER HANDY |
| Green Building Rough | 4/16/2026 | Approved | ALEXANDER HANDY |
| Insulation | 4/20/2026 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 4/27/2026 | Approved | TROY SANDERS |