6112 N MORELLA AVE 91606

Certificate Information: 6112 N MORELLA AVE 91606

Application / Permit
25014-20000-03519
Plan Check / Job No.
B25VN22414
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Addition to front of (e) dwelling.
Permit Issued
Issued on 9/21/2025
Issuing Office
Current Status
CofO Issued on 4/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2025 APPLICANT
Assigned to Plan Check Engineer 8/7/2025 SAMUEL GONZALEZ
Corrections Issued 8/8/2025 SAMUEL GONZALEZ
Applicant returned to address corrections 8/22/2025 SAMUEL GONZALEZ
Plan Check Approved 9/9/2025 SAMUEL GONZALEZ
Issued 9/21/2025 APPLICANT
No Progress 4/18/2026 ROBERTO PALACIOS-LOPEZ
CofO in Progress 4/18/2026 ROBERTO PALACIOS-LOPEZ
Permit Finaled 4/30/2026 RUBEN SALAS
CofO Issued 4/30/2026 RUBEN SALAS
Permit Finaled 4/30/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/19/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 8/20/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Segovia,, Felipe; Lic. No.: C41102 2622 DORSET DR      TORRANCE, CA 90503

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/8/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 10/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 10/21/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/23/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Insulation 10/23/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 12/18/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 1/5/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/5/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 1/13/2026 Approved ROBERTO PALACIOS-LOPEZ
Insulation 1/13/2026 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 1/13/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Drywall Nailing 1/20/2026 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 2/24/2026 Approved RAUL OLAGI
Final 3/26/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 3/26/2026 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 3/26/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 3/31/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 3/31/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 4/10/2026 Conditional Approval ROBERTO PALACIOS-LOPEZ