6112 N MORELLA AVE 91606
Certificate Information: 6112 N MORELLA AVE 91606
- Application / Permit
- 25014-20000-03519
- Plan Check / Job No.
- B25VN22414
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Addition to front of (e) dwelling.
- Permit Issued
- Issued on 9/21/2025
- Issuing Office
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2025 | SAMUEL GONZALEZ |
| Corrections Issued | 8/8/2025 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 8/22/2025 | SAMUEL GONZALEZ |
| Plan Check Approved | 9/9/2025 | SAMUEL GONZALEZ |
| Issued | 9/21/2025 | APPLICANT |
| No Progress | 4/18/2026 | ROBERTO PALACIOS-LOPEZ |
| CofO in Progress | 4/18/2026 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 4/30/2026 | RUBEN SALAS |
| CofO Issued | 4/30/2026 | RUBEN SALAS |
| Permit Finaled | 4/30/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/19/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Segovia,, Felipe; Lic. No.: C41102 | 2622 DORSET DR TORRANCE, CA 90503 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/8/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 10/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 10/21/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Insulation | 10/23/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Rough-Elec/Plmb/HVAC | 12/18/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 1/5/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 1/13/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 1/13/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 1/13/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 1/20/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 2/24/2026 | Approved | RAUL OLAGI |
| Final | 3/26/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 3/26/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 3/31/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 3/31/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 4/10/2026 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |