5461-5463 N VANALDEN AVE 91356

Certificate Information: 5461-5463 N VANALDEN AVE 91356

Application / Permit
25014-20000-03488
Plan Check / Job No.
B25VN22168
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL (ONLY 30" WALL TO REMAIN) AND ADDITION TO MAKE A 64'2"X90'10" 2-STORY SINGLE FAMILY DWELLING WITH AN TRELLISES, AN ATTACHED GARAGE, AND AN ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (e) (NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT) [1 OF 4]
Permit Issued
Issued on 2/5/2026
Issuing Office
Current Status
Issued on 2/5/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/1/2025 APPLICANT
Assigned to Plan Check Engineer 8/14/2025 MARVEL DELACRUZ
Corrections Issued 8/21/2025 MARVEL DELACRUZ
Quality Review Completed 8/21/2025 JASON HEALEY
Building Plans Picked Up 8/26/2025 APPLICANT
Applicant returned to address corrections 11/12/2025 MARVEL DELACRUZ
Plan Check Approved 2/5/2026 MARVEL DELACRUZ
Issued 2/5/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/3/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/3/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 9/3/2025 BIAINA HARITUNIAN
Sewer availability Cleared 9/3/2025 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 9/11/2025 KURT CORRAL
Trees in Parkway Cleared 10/1/2025 RICHARD SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/2/2026 Partial Inspection JOHN KIDWELL
Underground Mechanical 4/20/2026 Partial Approval JOHN KIDWELL
Deputy Drilled-In Anchors 5/1/2026 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 5/5/2026 Partial Approval JOHN KIDWELL
Deputy Drilled-In Anchors 5/7/2026 Conditional Approval ROBERT GOLD
Deputy Reinf. Concrete 5/7/2026 Conditional Approval ROBERT GOLD
Deputy Steel/Welding 5/7/2026 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 5/7/2026 Approved JOHN KIDWELL
Deputy Steel/Welding 5/8/2026 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 5/27/2026 Conditional Approval JOHN KIDWELL
Deputy Steel/Welding 6/24/2026 Partial Approval JOHN KIDWELL