9618 N LANGDON AVE 91343

Certificate Information: 9618 N LANGDON AVE 91343

Application / Permit
25014-20000-03484
Plan Check / Job No.
B25VN22144
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION FOR NEW BEDROOM, BATHROOMS AND CLOSET AND REMODEL TO (E) DETACHED ACCESSORY DWELLING UNIT PER GC 66232(a)(1).
Permit Issued
Issued on 9/12/2025
Issuing Office
Valley
Current Status
Issued on 9/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/1/2025 APPLICANT
Assigned to Plan Check Engineer 8/7/2025 JEROME MAGAT PALMA
Corrections Issued 8/7/2025 JEROME MAGAT PALMA
Building Plans Picked Up 8/11/2025 APPLICANT
Plan Check Approved 9/12/2025 ROSENDO MEDINA
Issued 9/12/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/25/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 8/26/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/15/2025 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 9/16/2025 Approved VINCENT HANLEY
PLUMBING-Rough 9/16/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Corrections Issued MICHAEL CORTEZ
Special/Order Compliance 10/3/2025 Partial Inspection RAUL OLAGI
BUILDING-Rough-Frame 10/21/2025 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 10/21/2025 Approved VINCENT HANLEY
HVAC-Rough 10/21/2025 Approved VINCENT HANLEY
MERV13>=Rough 10/21/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 10/28/2025 Approved VINCENT HANLEY
Green Building Rough 10/28/2025 Approved VINCENT HANLEY
Insulation 10/28/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 10/28/2025 Partial Approval VINCENT HANLEY
PLUMBING-Rough 10/28/2025 Approved VINCENT HANLEY
Drywall Nailing 10/31/2025 Approved MICHAEL CORTEZ
Shower Pan 10/31/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 11/3/2025 Partial Approval DAVID ANDERSON
Interior/Exterior Lathing 11/10/2025 Approved CHRISTOPHER MORFIN
Final 12/12/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Final 12/12/2025 Not Ready for Inspection WAYNE REGESTER
MERV13>=Final 12/12/2025 Not Ready for Inspection WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 12/12/2025 SGSOV Not Ready WAYNE REGESTER
Smoke Detectors 12/12/2025 Approved WAYNE REGESTER
ELECTRICAL-Final 12/16/2025 Approved VINCENT HANLEY
Final 12/16/2025 Corrections Issued VINCENT HANLEY
Green Building Final 12/16/2025 Approved VINCENT HANLEY
HVAC-Final 12/16/2025 Corrections Issued VINCENT HANLEY
MERV13>=Final 12/16/2025 Approved VINCENT HANLEY
PLUMBING-Final 12/16/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 12/16/2025 SGSOV Approved VINCENT HANLEY