5122 N BILOXI AVE 91601

Certificate Information: 5122 N BILOXI AVE 91601

Application / Permit
25014-20000-03457
Plan Check / Job No.
B25VN22032
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD IRREG SHAPED PATIO COVER TO (E) SFD
Permit Issued
Issued on 8/22/2025
Issuing Office
Current Status
CofO Issued on 5/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2025 APPLICANT
Assigned to Plan Check Engineer 8/7/2025 JEROME MAGAT PALMA
Corrections Issued 8/8/2025 JEROME MAGAT PALMA
Building Plans Picked Up 8/12/2025 APPLICANT
Plan Check Approved 8/20/2025 OMAR GARNICA
Issued 8/22/2025 APPLICANT
CofO in Progress 4/3/2026 ROBERTO PALACIOS-LOPEZ
CofO Issued 5/7/2026 RUBEN SALAS
Permit Finaled 5/7/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/20/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 8/20/2025 DERRICK MAGEE

Contact Information

Contractor Golden West Remodeling Inc; Lic. No.: 1102610-B 7007 COZYCROFT AVE      WINNETKA, CA 91306
Engineer Braun,, Jason; Lic. No.: C70948 14390 SHAWNEE ST      MOORPARK, CA 93021

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/8/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 9/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 9/10/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/22/2025 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 10/22/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 10/22/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/11/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 3/11/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 3/11/2026 Approved ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 3/11/2026 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 3/11/2026 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 3/11/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 3/25/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 3/25/2026 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 3/25/2026 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 3/25/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 4/3/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/3/2026 SGSOV Approved ROBERTO PALACIOS-LOPEZ