10607 N DEMPSEY AVE 91344

Certificate Information: 10607 N DEMPSEY AVE 91344

Application / Permit
25014-20000-03425
Plan Check / Job No.
B25VN21828
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Addition and remodel to existing 1-story S.F.D. and attached garage.
Permit Issued
Issued on 12/16/2025
Issuing Office
Current Status
CofO Issued on 5/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2025 APPLICANT
Assigned to Plan Check Engineer 8/15/2025 CAROLEAN BASMA
Corrections Issued 8/18/2025 CAROLEAN BASMA
Plan Check Approved 12/3/2025 CAROLEAN BASMA
Issued 12/16/2025 APPLICANT
CofO in Progress 4/7/2026 CHRISTOPHER ROJAS
CofO Issued 5/14/2026 RUBEN SALAS
Permit Finaled 5/14/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/20/2025 BIAINA HARITUNIAN
Sewer availability Cleared 10/20/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 11/14/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/22/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/5/2026 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 1/26/2026 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/26/2026 Approved KIRK SANDERS
PLUMBING-Rough 1/26/2026 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 2/6/2026 Approved KIRK SANDERS
ELECTRICAL-Rough 2/6/2026 Approved KIRK SANDERS
Green Building Rough 2/6/2026 Partial Approval KIRK SANDERS
PLUMBING-Rough 2/6/2026 Approved KIRK SANDERS
Green Building Rough 2/13/2026 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 2/13/2026 Partial Inspection MICHAEL CORTEZ
Shower Pan 2/13/2026 Approved MICHAEL CORTEZ
Insulation 2/20/2026 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 2/20/2026 Corrections Issued KEVIN BERBERYAN
Drywall Nailing 2/25/2026 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 2/25/2026 Approved MICHAEL CORTEZ
Final 3/26/2026 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 3/26/2026 Approved KEVIN BERBERYAN
Green Building Final 3/26/2026 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 3/26/2026 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 3/26/2026 Approved KEVIN BERBERYAN
Final 4/3/2026 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 4/3/2026 Approved CHRISTOPHER ROJAS