16552 W DEVONSHIRE ST 91344

Certificate Information: 16552 W DEVONSHIRE ST 91344

Application / Permit
25014-20000-03398
Plan Check / Job No.
B25VN21553
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE AND NEW ADDITION INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(b)(1). CONSTRUCTION DESIGN PER ENGR.
Permit Issued
Issued on 10/17/2025
Issuing Office
Current Status
CofO in Progress on 5/14/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/28/2025 APPLICANT
Assigned to Plan Check Engineer 8/5/2025 HAYATO TSUCHIYA
Corrections Issued 8/5/2025 HAYATO TSUCHIYA
Building Plans Picked Up 8/8/2025 APPLICANT
Plan Check Approved 10/17/2025 ISIS ARGUETA
Issued 10/17/2025 APPLICANT
CofO in Progress 5/14/2026 CHRISTOPHER ROJAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/2/2025 ERIK BEASLEY
Construction near power lines Cleared 9/9/2025 GEVORK KARAPETYAN
Address approval Cleared 9/10/2025 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 9/18/2025 MICHAEL BROWN
Sewer availability Cleared 9/18/2025 MICHAEL BROWN
GPI Written Notices Cleared 10/17/2025 HAYATO TSUCHIYA
Grading Pre-Inspection Cleared 10/17/2025 HAYATO TSUCHIYA

Contact Information

Contractor Owner-Builder       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/3/2025 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 11/3/2025 Partial Approval CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 11/7/2025 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 11/7/2025 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 11/7/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 2/26/2026 Partial Approval KIRK SANDERS
Special/Order Compliance 2/26/2026 Corrections Issued KIRK SANDERS
Deputy Wood Construction 3/11/2026 Conditional Approval JOSE AVILA
BUILDING-Rough-Frame 3/17/2026 Partial Inspection CHRISTOPHER ROJAS
Gas Test 3/17/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 3/17/2026 Approved CHRISTOPHER ROJAS
HVAC-Rough 3/17/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 3/17/2026 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/26/2026 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 3/26/2026 Corrections Issued CHRISTOPHER ROJAS
HVAC-Rough 3/26/2026 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/1/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 4/1/2026 Approved CHRISTOPHER ROJAS
Insulation 4/1/2026 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/1/2026 Partial Approval CHRISTOPHER ROJAS
Insulation 4/3/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/3/2026 Approved CHRISTOPHER ROJAS
Pre-Inspection 4/3/2026 Approved CHRISTOPHER ROJAS
Drywall Nailing 4/8/2026 Approved JOSE AVILA
ELECTRICAL-Final 5/7/2026 Corrections Issued CHRISTOPHER ROJAS
Final 5/7/2026 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 5/7/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 5/7/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 5/7/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 5/11/2026 Approved DAVID MATSON
HVAC-Final 5/11/2026 Approved DAVID MATSON
PLUMBING-Final 5/11/2026 Approved DAVID MATSON
Final 5/14/2026 OK to Issue CofO CHRISTOPHER ROJAS
Footing/Foundation/Slab 5/14/2026 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 5/14/2026 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 5/14/2026 Approved CHRISTOPHER ROJAS