17522 W KITTRIDGE ST 91406
Certificate Information: 17522 W KITTRIDGE ST 91406
- Application / Permit
- 25014-20000-03388
- Plan Check / Job No.
- B25VN21529
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. ADDITION AND REMODEL TO (E) SFD, ALL WORK PER ENG.
- Permit Issued
- Issued on 8/26/2025
- Issuing Office
- Current Status
- Issued on 8/26/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2025 | LUISANGEL VALENZUELA |
| Corrections Issued | 8/1/2025 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 8/20/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 8/24/2025 | SARKIS HARABEDIAN |
| Issued | 8/26/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/8/2025 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2025 | TAL SHEMEN |
| Sewer availability | Cleared | 8/11/2025 | TAL SHEMEN |
Contact Information
| Contractor | Simple Choice Construction Inc; Lic. No.: 1076567-B | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/22/2025 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 9/22/2025 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 10/17/2025 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 10/17/2025 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2025 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 10/31/2025 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 12/1/2025 | Corrections Issued | JON MCHUGH |
| Deputy Drilled-In Anchors | 12/3/2025 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2025 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Partial Approval | JON MCHUGH |
| ELECTRICAL-Rough | 12/22/2025 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2025 | Partial Approval | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 12/22/2025 | Corrections Issued | JON MCHUGH |
| Deputy Drilled-In Anchors | 12/23/2025 | Conditional Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 1/12/2026 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 1/12/2026 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 1/12/2026 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 1/12/2026 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 1/14/2026 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 1/14/2026 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 1/14/2026 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2026 | Partial Approval | JON MCHUGH |
| Insulation | 1/20/2026 | Partial Approval | JON MCHUGH |
| Shower Pan | 1/20/2026 | Approved | JON MCHUGH |
| Drywall Nailing | 1/26/2026 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2026 | Partial Approval | JON MCHUGH |
| Interior/Exterior Lathing | 1/26/2026 | Partial Approval | JON MCHUGH |
| Special/Order Compliance | 2/4/2026 | Not Ready for Inspection | JON MCHUGH |
| Footing/Foundation/Slab | 2/9/2026 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 2/25/2026 | Corrections Issued | JON MCHUGH |
| Insulation | 3/2/2026 | Not Ready for Inspection | JON MCHUGH |
| Pre-Inspection | 3/2/2026 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 3/6/2026 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 3/6/2026 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 3/11/2026 | Not Ready for Inspection | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 3/11/2026 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 3/16/2026 | Corrections Issued | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 3/16/2026 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 3/19/2026 | Approved | JON MCHUGH |
| Drywall Nailing | 3/25/2026 | Approved | JON MCHUGH |
| Insulation | 3/25/2026 | Approved | JON MCHUGH |
| Final | 5/4/2026 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 5/4/2026 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 5/4/2026 | Not Ready for Inspection | JON MCHUGH |
| Final | 5/19/2026 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 5/19/2026 | Approved | JON MCHUGH |
| Final | 5/26/2026 | Partial Approval | JON MCHUGH |