1902 S WESTGATE AVE 90025

Certificate Information: 1902 S WESTGATE AVE 90025

Application / Permit
25014-20000-03379
Plan Check / Job No.
B25VN21493
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ATTACHED COVERED PATIO. EXTERIOR REMODEL TO ADD NEW (2) BEDROOM WINDOWS FOR SINGLE FAMILY DWELLING.
Permit Issued
Issued on 8/18/2025
Issuing Office
Current Status
CofO Issued on 11/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/25/2025 APPLICANT
Assigned to Plan Check Engineer 8/4/2025 JESSE ARELLANO
Corrections Issued 8/4/2025 JESSE ARELLANO
Building Plans Picked Up 8/6/2025 APPLICANT
Applicant returned to address corrections 8/15/2025 GIOVANNY CHAVEZ
Plan Check Approved 8/18/2025 NAREG ATARIAN
Issued 8/18/2025 APPLICANT
Permit Finaled 11/29/2025 RICHARD STEINBACH
CofO Issued 11/29/2025 RICHARD STEINBACH
Permit Finaled 11/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/14/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 8/14/2025 MICHAEL BROWN

Contact Information

Contractor California Green Energy; Lic. No.: 896465-B 17000 VENTURA BLVD STE 203      ENCINO, CA 91316
Engineer Tangonan,, Jeffrey Tolentino; Lic. No.: C83522 17770 CAPE JASMINE RD      CANYON COUNTRY, CA 91387

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/28/2025 Conditional Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 9/12/2025 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/12/2025 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 9/12/2025 Approved ARAM AVEDISIAN
Green Building Rough 9/12/2025 Not Ready for Inspection ARAM AVEDISIAN
Green Building Rough 9/15/2025 Not Ready for Inspection ARAM AVEDISIAN
Wood Frame 9/15/2025 Approved ARAM AVEDISIAN
Drywall Nailing 9/23/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 9/23/2025 Approved ARAM AVEDISIAN
Final 10/29/2025 Not Ready for Inspection MICHAEL ALLEN
Green Building Final 10/29/2025 Approved MICHAEL ALLEN
Green Building Rough 10/29/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 10/29/2025 Corrections Issued MICHAEL ALLEN
Wood Frame 10/29/2025 Approved MICHAEL ALLEN
Final 11/10/2025 Conditional Approval MICHAEL ALLEN
Smoke Detectors 11/10/2025 Approved MICHAEL ALLEN