8337 N ECHELON PL 91352
Certificate Information: 8337 N ECHELON PL 91352
- Application / Permit
- 25014-20000-03374
- Plan Check / Job No.
- B25VN21471
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, (N) ADDITION TO ONE STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 10/3/2025
- Issuing Office
- Current Status
- Issued on 10/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2025 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 8/6/2025 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 9/16/2025 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 10/1/2025 | HAYATO TSUCHIYA |
| Plan Check Approved | 10/3/2025 | ISIS ARGUETA |
| Issued | 10/3/2025 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/7/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 8/13/2025 | RYAN CASTRO |
| Grading Pre-Inspection | Cleared | 8/13/2025 | ALEXANDER HELFER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/24/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 10/28/2025 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 10/31/2025 | Approved | DAVID ANDERSON |
| Wood Frame | 12/19/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Wood Frame | 12/24/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2025 | Partial Approval | DAVID ANDERSON |
| Special/Order Compliance | 12/31/2025 | Corrections Issued | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 1/5/2026 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2026 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 1/30/2026 | Corrections Issued | DAVID ANDERSON |
| Wood Frame | 1/30/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Wood Frame | 3/3/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Wood Frame | 3/10/2026 | Corrections Issued | DAVID MATSON |
| ELECTRICAL-Rough | 3/12/2026 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 3/19/2026 | Approved | DAVID ANDERSON |
| Green Building Rough | 3/19/2026 | Approved | DAVID ANDERSON |
| Insulation | 3/24/2026 | Approved | DAVID ANDERSON |
| Drywall Nailing | 3/27/2026 | Approved | RAUL OLAGI |