8337 N ECHELON PL 91352

Certificate Information: 8337 N ECHELON PL 91352

Application / Permit
25014-20000-03374
Plan Check / Job No.
B25VN21471
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, (N) ADDITION TO ONE STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 10/3/2025
Issuing Office
Current Status
Issued on 10/3/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/25/2025 APPLICANT
Assigned to Plan Check Engineer 8/6/2025 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 8/6/2025 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 9/16/2025 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 10/1/2025 HAYATO TSUCHIYA
Plan Check Approved 10/3/2025 ISIS ARGUETA
Issued 10/3/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 8/7/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/8/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 8/13/2025 RYAN CASTRO
Grading Pre-Inspection Cleared 8/13/2025 ALEXANDER HELFER

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/24/2025 Conditional Approval JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 10/28/2025 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 10/31/2025 Approved DAVID ANDERSON
Wood Frame 12/19/2025 Not Ready for Inspection MATTHEW NELSON
Wood Frame 12/24/2025 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 12/31/2025 Partial Approval DAVID ANDERSON
Special/Order Compliance 12/31/2025 Corrections Issued DAVID ANDERSON
Deputy Drilled-In Anchors 1/5/2026 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 1/5/2026 Partial Approval DAVID ANDERSON
ELECTRICAL-Rough 1/30/2026 Corrections Issued DAVID ANDERSON
Wood Frame 1/30/2026 Not Ready for Inspection DAVID ANDERSON
Wood Frame 3/3/2026 Not Ready for Inspection DAVID ANDERSON
Wood Frame 3/10/2026 Corrections Issued DAVID MATSON
ELECTRICAL-Rough 3/12/2026 Partial Approval DAVID ANDERSON
BUILDING-Rough-Frame 3/19/2026 Approved DAVID ANDERSON
Green Building Rough 3/19/2026 Approved DAVID ANDERSON
Insulation 3/24/2026 Approved DAVID ANDERSON
Drywall Nailing 3/27/2026 Approved RAUL OLAGI