6915 N CALHOUN AVE 91405
Certificate Information: 6915 N CALHOUN AVE 91405
- Application / Permit
- 25014-20000-03362
- Plan Check / Job No.
- B25VN21365
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED INT/EXT REMODEL W/ ROOM ADDITION AT THE REAR & FRONT PATIO COVER ADDN TO EX 1-STORY SFD. CONSTRUCTION DESIGN PER ENGR.
- Permit Issued
- Issued on 10/30/2025
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 6/1/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2025 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 8/1/2025 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 8/4/2025 | APPLICANT |
| Applicant returned to address corrections | 10/29/2025 | HAYATO TSUCHIYA |
| Plan Check Approved | 10/30/2025 | NAREG ATARIAN |
| Issued | 10/30/2025 | APPLICANT |
| CofO in Progress | 6/1/2026 | JOSE AVILA |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/29/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/29/2025 | BIAINA HARITUNIAN |
| ZA Case | Cleared | 9/2/2025 | DALIA MOKAYED |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ananian,, Vatche; Lic. No.: C79073 | 19528 VENTURA BLVD #374 TARZANA, CA 91356 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/10/2025 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 12/26/2025 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 12/26/2025 | Partial Approval | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 12/30/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 12/30/2025 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 1/5/2026 | Partial Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2026 | Partial Approval | RYAN SALAZAR |
| Wood Frame | 1/22/2026 | Partial Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/30/2026 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/30/2026 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 1/30/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/30/2026 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/3/2026 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 2/3/2026 | Approved | JACK KARGODORIAN |
| Green Building Rough | 2/3/2026 | Approved | JACK KARGODORIAN |
| Wood Frame | 2/3/2026 | Partial Approval | JACK KARGODORIAN |
| Insulation | 2/26/2026 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 2/26/2026 | Partial Approval | KIRK SANDERS |
| Drywall Nailing | 3/2/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/2/2026 | Partial Approval | VINCENT HANLEY |
| Shower Pan | 4/3/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/7/2026 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/18/2026 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 5/18/2026 | Approved | VINCENT HANLEY |
| Final | 5/18/2026 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 5/18/2026 | Approved | VINCENT HANLEY |
| Green Building Final | 5/18/2026 | Approved | VINCENT HANLEY |
| HVAC-Final | 5/18/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 5/18/2026 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 5/18/2026 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 5/18/2026 | Approved | VINCENT HANLEY |
| Final | 5/27/2026 | Corrections Issued | VINCENT HANLEY |
| Final | 6/1/2026 | OK to Issue CofO | JOSE AVILA |