4414 S WESTLAWN AVE 90066

Certificate Information: 4414 S WESTLAWN AVE 90066

Application / Permit
25014-20000-03360
Plan Check / Job No.
B25VN21331
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED MAJOR INT/EXT REMODEL WITH IRR SHAPED ADDN. CONVERT EX CONVENTIONAL ROOF FRAMING INTO VAULTED CEILING OVER EX DWELLING WITH NEW STEEL BEAM & RE-INFORCE EXISTING ROOF FRAMING PER PLAN. NO CHANGE TO EX ROOF SLOPE/ORIENTATION/BLDG HEIGHT. FIRE SPRINKLER NFPA 13D
Permit Issued
Issued on 9/11/2025
Issuing Office
Valley
Current Status
CofO Issued on 6/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2025 APPLICANT
Assigned to Plan Check Engineer 7/30/2025 HAYATO TSUCHIYA
Corrections Issued 7/30/2025 HAYATO TSUCHIYA
Building Plans Picked Up 7/31/2025 APPLICANT
Applicant returned to address corrections 8/20/2025 MOHAMMAD ESMAILI
Plan Check Approved 8/29/2025 NAREG ATARIAN
Issued 9/11/2025 APPLICANT
CofO in Progress 6/23/2026 MORRIS JACKSON
Permit Finaled 6/23/2026 RICHARD STEINBACH
CofO Issued 6/23/2026 RICHARD STEINBACH
Permit Finaled 6/23/2026 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/14/2025 DERRICK MAGEE
Sewer availability Cleared 8/14/2025 DERRICK MAGEE
Specific Plan Cleared 8/14/2025 RICHARD WOO
Eng Process Fee Ord 176,300 Cleared 8/15/2025 DERRICK MAGEE

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng D; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/17/2025 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 10/29/2025 Corrections Issued RUBEN RIVAS
PLUMBING-Rough 10/29/2025 Corrections Issued RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 10/31/2025 Corrections Issued RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 11/3/2025 Partial Approval RUBEN RIVAS
PLUMBING-Rough 11/3/2025 Approved RUBEN RIVAS
Insulation 11/5/2025 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Partial Approval RUBEN RIVAS
Deputy Drilled-In Anchors 12/4/2025 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 12/11/2025 Partial Approval ANTHONY EGSON
PLUMBING-Rough 12/15/2025 Approved ANTHONY EGSON
ELECTRICAL-Rough 12/16/2025 Approved ANTHONY EGSON
HVAC-Rough 12/18/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 1/12/2026 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 1/12/2026 Approved ANTHONY EGSON
BUILDING-Rough-Frame 1/22/2026 Approved EUGENE CASSIDY
Interior/Exterior Lathing 1/30/2026 Corrections Issued DAKOTA LOW
Interior/Exterior Lathing 2/3/2026 Partial Approval DAKOTA LOW
Insulation 2/12/2026 Approved DAKOTA LOW
Shower Pan 3/3/2026 Not Ready for Inspection ANTHONY EGSON
Shower Pan 3/5/2026 Approved ANTHONY EGSON
Drywall Nailing 3/6/2026 Approved ANTHONY EGSON
Interior/Exterior Lathing 3/9/2026 Approved ANTHONY EGSON
Service/Power Release 5/7/2026 Not Ready for Inspection ANTHONY EGSON
Service/Power Release 5/19/2026 Approved MORRIS JACKSON
PLUMBING-Final 5/21/2026 Approved MORRIS JACKSON
HVAC-Final 6/17/2026 Approved MORRIS JACKSON
Final 6/22/2026 OK to Issue CofO MORRIS JACKSON
Footing/Foundation/Slab 6/22/2026 Approved MORRIS JACKSON
Green Building Final 6/22/2026 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 6/22/2026 SGSOV Approved MORRIS JACKSON
Smoke Detectors 6/22/2026 Approved MORRIS JACKSON