22120-22122 W COSTANSO ST 91364

Certificate Information: 22120-22122 W COSTANSO ST 91364

Application / Permit
25014-20000-03352
Plan Check / Job No.
B25VN21263
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO ENLARGE THE (E) BEDROOM AND ADD A NEW BATHROOM
Permit Issued
Issued on 7/29/2025
Issuing Office
Current Status
CofO Issued on 4/6/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2025 APPLICANT
Assigned to Plan Check Engineer 7/24/2025 ALEC MOUSAKHANIAN
Corrections Issued 7/24/2025 ALEC MOUSAKHANIAN
Applicant returned to address corrections 7/25/2025 ANGELICA DAVE
Plan Check Approved 7/29/2025 ALEC MOUSAKHANIAN
Issued 7/29/2025 APPLICANT
CofO in Progress 1/13/2026 JOHN HAYES
CofO in Progress 1/13/2026 JOHN HAYES
Permit Finaled 4/6/2026 JOHN JANSON
CofO Issued 4/6/2026 JOHN JANSON
Permit Finaled 4/6/2026 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/24/2025 JEANIE LAM
Roof/Waste drainage to street Cleared 7/24/2025 WALLIE JONG
Grading Pre-Inspection Cleared 7/29/2025 ALEXANDER HELFER

Contact Information

Contractor Dream Remodeling Inc; Lic. No.: 889254-B 22704 VENTURA BLVD #444      WOODLAND HILLS, CA 91411

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/5/2025 Approved GEVORK IPCHYAN
PLUMBING-Rough 8/5/2025 Not Ready for Inspection GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/11/2025 Partial Approval SEAN WIRCH
PLUMBING-Rough 8/11/2025 Corrections Issued SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 8/13/2025 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 8/20/2025 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 8/20/2025 Approved JOHN HAYES
PLUMBING-Rough 8/20/2025 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 8/25/2025 Partial Approval MORRIS JACKSON
Green Building Rough 8/25/2025 Not Ready for Inspection MORRIS JACKSON
HVAC-Rough 8/25/2025 Approved MORRIS JACKSON
BUILDING-Rough-Frame 8/27/2025 Approved JOHN HAYES
Green Building Rough 8/27/2025 Approved JOHN HAYES
Insulation 8/27/2025 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 8/27/2025 Partial Approval JOHN HAYES
Insulation 8/29/2025 Partial Approval SCOTT SOBEL
Shower Pan 8/29/2025 Approved SCOTT SOBEL
Insulation 9/3/2025 Approved SCOTT SOBEL
Interior/Exterior Lathing 9/3/2025 Approved SCOTT SOBEL
Drywall Nailing 9/5/2025 Approved SCOTT SOBEL
Final 9/23/2025 OK to Issue CofO JOHN HAYES
Green Building Final 9/23/2025 Approved JOHN HAYES
Smoke Detectors 9/23/2025 Approved JOHN HAYES
Final 1/13/2026 OK to Issue CofO JOHN HAYES