6550 N BEEMAN AVE 91606
Certificate Information: 6550 N BEEMAN AVE 91606
- Application / Permit
- 25014-20000-03341
- Plan Check / Job No.
- B25VN21215
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert detached garage to ADU with an addition the the ADU per LAMC 12.22 A.33(b)(1).
- Permit Issued
- Issued on 9/9/2025
- Issuing Office
- Current Status
- CofO Issued on 4/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2025 | NEHEMIAS RAMOS |
| Corrections Issued | 8/12/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 9/9/2025 | DANIEL SMILEY |
| Issued | 9/9/2025 | APPLICANT |
| CofO in Progress | 3/17/2026 | WAYNE REGESTER |
| CofO Issued | 4/2/2026 | RUBEN SALAS |
| Permit Finaled | 4/2/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/21/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 8/21/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 9/5/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 9/5/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/29/2025 | Approved | WAYNE REGESTER |
| Deputy Drilled-In Anchors | 10/1/2025 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 10/6/2025 | Approved | WAYNE REGESTER |
| Underground Mechanical | 10/6/2025 | Approved | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2025 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 11/19/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Rough | 11/19/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 11/25/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 11/25/2025 | Approved | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2025 | Approved | WAYNE REGESTER |
| Insulation | 12/9/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 12/9/2025 | Approved | WAYNE REGESTER |
| Drywall Nailing | 12/12/2025 | Approved | MICHAEL CORTEZ |
| Final | 3/13/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Footing/Foundation/Slab | 3/13/2026 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 3/13/2026 | SGSOV Not Required | WAYNE REGESTER |
| Smoke Detectors | 3/13/2026 | Approved | WAYNE REGESTER |
| ELECTRICAL-Final | 3/17/2026 | Approved | WAYNE REGESTER |
| Final | 3/17/2026 | OK to Issue CofO | WAYNE REGESTER |
| Green Building Final | 3/17/2026 | Approved | WAYNE REGESTER |
| HVAC-Final | 3/17/2026 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 3/17/2026 | Approved | WAYNE REGESTER |